  1. Excuse my ignorance but I assumed the 2010-2011 drilling was to optimize a starter pit and define the paramount zone. In the webcast Elmer said the starter pit will be in the Liard zone, with the potential to mine high grades in the paramount zone. I assume these zones will be mined interchangeably using a conveyor system? Looking at the new slides both zones deff have a high grade component which will optimize the economics in the early years. I also found a demeanor to Elmer's voice which suggested there is little hurry to drill like crazy. Proving the district has taken a central role and why wouldn't it? Elmer said, Teck or any other majors looking to get involved in the project want century scale projects. Properties in the option agreement are as good as sold IMO. What is happening now has everything to do with what the structure of the future JV will entail. The terms of the schaft creek buyout and future JV must be lucrative enough for us to avoid "causing problems" with the Teck, copper fox relationship. Actually the new JV has the potential to outshine the original agreement. We will tighten the share structure, have insider control, carry a huge balance sheet and have the retail confidence obtained by the original sale in JV #1. We will also have the largest mine in N America next door :). My only worry is how we will sell JV #2. With decades of reserves available from the sale of Schaft creek what insentive does Teck have to buy JV #2 anytime soon. I would prefer to avoid this senario altogether by creating a trigger following a RE. 10% insitu straight up lol
    1. Tommy2tone... you are right, 2011 was about optimizing the starter pit potential and exploring Paramount. Paramount was too big to finish defining last year - nice problem. I don't think a lot changed in terms of finding really good grades at shallow depths in either Paramount or Liard beyond what was defined previously.

      I understood the 'demeanor in Elmer's voice which suggested there is little hurry to drill like crazy' to mean that there is little incentive to keep drilling at the Paramount and Main zones to keep adding pounds when the same drilling effort could be directed at adding/proving whole new mineralized zones.

      I also got that from his response to Webgog's questions. New found minerals 600m down are not as good as new found minerals in a new zone at shallower depths. Discounting that deep stuff (NPV) means that there is less bang for each $1 spent drilling. A lot less bang when compared to proving a new mineralized zone has mining potential (good grades and depths).

      For example. $500,000,000 net income from mining is worth $462,962,963 when discounted 8% for one year. That same $500M of income is only worth $49,688,666 when discounted for 30 years at 8%. In a NPV context, the metal at the bottom of the mine extracted 30 years after startup is worth about 10% of that to us today.

      So, do you want to keep pumbing the depths of Schaft or do you want to prove a whole new SC sized zone with mining potential?

      In the 2008 PFS, there are 5 starter pits. The first pit (P611) opens up in Liard, in the region of 2011 DDH 419. This area is good for starter since the grades are better than average, very close to the surface and don't require a lot of surface preparation due to the relatively gentle terrain.

      Paramount also had a starter pit in the 2008 PFS but it opened up towards the end of the first 5 years. Part of that 'delay' could be that some of the slope of above the Paramount starting area needed to be cut and benched to stabilize it before digging deeply below that slope.

      This image comes out of the PFS and shows the mine at the end of year 5 of operation. Pit P611 is the first pit and takes out much of the top of Liard/Main. DDH 419 is very roughly located near the last "1" in the label "P611".

      Pit "P631" is generally located in the Paramount zone and encompassed the northern extent of the 2011 drilling in Paramount. Therefore little change to our starting pit scenarios.