I've been meaning to ask this question of "The More Knowlegable" for a while. Does it really take over a year and a half to produce a BFS given that those who are preparing the Report are professionals and supposedly doing this for a living? Yes, the starter pit location may have changed; yes we are including the May 31 revised R/E numbers; yes we are doing a myriad of other things which we may not be privy to .... but

The Report was originally due early last year, then last fall and then by calender year end. And then by March 31 this year. And now by mid-late summer. In March, we were told the Report was weeks behind, not just a missed deadline by a few days because of manpower issues. OK. Well we are months behind that deadline now. Which begs the question. What on earth has been going on? If the Report ends up being 8-10,000 pages, well we know there is a lot of descriptive fluff which would have been ready last fall. We know that a lot of the calculations are computer-modelled and standard format. We know a lot of verbiage has been pre-written. We know that various costs are available for any Feasibility Study - we are not a new situation. And we hope that the Report authors are experienced and knowledgable. Now throw in Jim Gray on a very regular basis (posing all the Teck questions as well as his own input) and throw in regular CUU management meetings. Don't forget, TetraTech was very "embarrassed" about dropping the ball in March and would want to get this one off their plate. Yes we want to "get it right the first time" but at what point do you draw the line and call it complete. Economic conditions/pricings/costing change regularly.

So I'm asking ... what is so different about our BFS than others that have been started, completed and published? Did we get anything for the money we spent last year?

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. I'm not one of the "more knowledgeable" but I can answer some of your questions.

    Yes, a full feasibility can easily take over a year and a half to complete. Scope creep can be a nasty thing for project deadlines. Schaft Creek likely started out at 120,000 tpd, then moved up to 150,000 tpd, and may have moved up again. Combine that with the changing block models from the Resource Estimates and you can see why we've had some delays. The more they drill, the bigger the project gets. That being said, our Feasibility Study is taking considerably longer than other companies I track. Here's a comparison of the time to produce feasibility studies for other projects:

    QB2 (Teck) = 135,000 tpd = 20 months

    Relincho (Teck) = 140,000 tpd = 16 months

    Santo Domingo (Capstone) = 63,500 tpd = 14 months

    Schaft Creek = 120,000+ tpd = 32 months

    I'm okay with the past delays that we've seen but the company has done a terrible job of explaining them. I'm led to believe that either their project management skills are very poor, they've had a considerable amount of re-work, or they are intentionally stalling. My guess is the second option (re-work). As I said before, if we don't get any news this week I'll be emailing the company asking to release more info on their deadlines.

  2. Agreed. So the question is why? Could it be as simple as the 3 year average metals pricing?

    If you had one shot to get it right and could materially improve your valuation by simple delay, allowing the 3 year average price to increase, would you? An average improvement of $0.50 lb cu would add billions....and that is only copper!