A little bird sent me a copy of the Feasibility Study and I put 3 copies on the cloud for folks to access. If one link doesn't work because of high traffic, try the next. Once you've clicked and downloaded the document, look for it either at the bottom of your screen or in your "Download" folder under My Documents on your PC. Enjoy
"A summarized Schedule is provided...with the key dates as follows:
kick-off feasibility study: January 19, 2010
feasibility study ocmpleted: December 2012
Teck review period completed: April 2013
.....
What clock are they using for this date? That is a few months ahead of June 4th per 120 days from today...
Didn't someone quote Mike from the Vancouver conference as saying something about the clock to the effect of "what makes you think it hasn't started already"?
They must have intended for Teck to receive BFS on Dec. 21, 2012 which would bring the date to April 2013. However, decided to wait till condensed version?
Didn't someone quote Mike from the Vancouver conference as saying something about the clock to the effect of "what makes you think it hasn't started already"?
Chappy, funny you should mention that. I didn`t want to post this here because I wasn`t sure if he was just joking or not but I did pm several people about his comment. When I asked him about the 120days starting this was the first thing he said. Was it an opps on his part? Did the clock start already? The report does say that the feasibility was completed in Dec 2012 and I imagine Teck may have been given the copy then. If there were no major changes between then and now perhaps the clock has started already.
I don't know what to think of this statement about 2012 Aerial Mags. My bold and underline. I thought this was all plunked into the Mira studies and the company reported that the Mira work was done??? This is either an error in the text (e.g. a copy paste error from an earlier report) or the 2012 magnetics are still being studied. No mention of the Mira work at all in this report. What gives??
9.5.2 Phase II, 2012 [pg 9-11]
A follow-up survey to the 2011 helicopter-borne magnetic field survey was completed by Precision GeoSurveys in May 2012. The purpose of Phase II was to extend the limits to the north and south of the area covered in Phase I. A total of 2, 524 line kilometers were flown with 200 m line spacings. Results were still pending at the time of preparing this report.
Continue drilling into the Discovery Zone, situated approximately 1,200 m northwest of the deposit, as a follow-up to mineralization encountered in drillhole 2011CF422. While a considerable amount of drilling is required to delineate and determine the significance of this discovery, the continuity of the mineralization and its location on the western edge of a large strong chargeability anomaly suggests this zone could host significant mineralization
Perform drilling proximal to holes 2011CF423 and 2011CF424, as a follow-up to newly encountered mineralization. The area is located west of West Breccia Zone and outside of the currently defined deposit and western wall of the proposed open pit. Information gained could provide insight into the geological interpretation of the West Breccia Zone and could expand the mineral resource estimate.