Timelines

Here is a quick list of some timelines that have been provided by Copper Fox and the Feasibility Study. It's obvious that some of these items have been pushed back.

April 2013 - Financing period complete

June 2013 - Basic engineering and start ordering long lead items

July 2013 - Baseline aquatics report complete

??? - Annual General Meeting

Q3 2013 - EA application and EIS submitted (includes THREAT report, water quality predictions, etc)

December 2013 - Start of detailed engineering and procurement activities

May 2014 - BC Hydro Facilities Study complete

At this point we don't really know what they are discussing with Teck so it's difficult to criticize them on the first couple of items. I am concerned that they will miss their Q3 target for the EA application. We haven't seen any new documents posted on the Project Information Center and we know they have several items outstanding. I hope they are dedicating all their resources to getting the EA submitted because this is a critical item in their timeline. For comparison, Seabridge Gold submitted their 25,000 page EA application on Feb 1, the preliminary review was completed June 4, and they expect approval in June 2014.

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. It looks like our deadline accuracy on the EA application is no better than the Feasibility Study (possibly because they are related?).

    In August 2011 we were planning on submitting the EA in Q4 2011.

    In May 2012 we were planning on submitting the EA in Q4 2012.

    In April 2013 we were planning on submitting the EA in Q3 2013.

    Should we start placing bets?

  2. We haven't seen any new documents posted on the Project Information Center and we know they have several items outstanding.

    They did recently post a 2011 hydrogeology study on the website. You can see it in the 2013 section.

    To be fair, they only learned about the requirements for the Highway 37 to be included in the environmental assessment on August 29th, 2012 and Shane said this would be no problem but would be a considerable amount of extra work. I thought we were told it might delay the whole project for another year.

    I thought our EA ran to something like 100,000 pages. It is immense.

    1. Good catch on the hydrology report. I did not notice that it had been posted on their website.

      The assessment on highway 37 is definitely a valid reason to delay the EA application. Environmental paperwork often runs behind schedule for all projects so it's not a big surprise that our deadlines from the past have been missed. I do hope they can hit their target of Q3 though.