The now even more important and desirable/ valuable SC specifics? Low environmental impact, no direct drain into river systems, no Fish Habitat, except for *Red Herrings!

*SC geology & location is unlike any other deposit in Canada although not devoid of it's own challenges. So imo, a direct slam against our specifics is not valid or warranted.

Those "in the know" will be well aware of this fact, and likely will pay more big time for our deposit.

Someone here recently mentioned newer reg's. which now will likely be amended to better protect sensitive areas in the future. For miners (not us) this will be incorporated as part of costing out margins on operations.

keeping the faith,

sb

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

    1. has fat lady sung yet bb?

      jimo, we will be much closer to negative cost pp figures in conclusion of our interest in sc. (can't see BMO being so far out to lunch as apparent right now either).

      sb

    2. Really? 32 cents? Didn't you started investing in CUU back in November 2013? If that's the case, the FS was out and the copper cost is closer to a $1 instead.

      I know. Frustrating because I've only been a shareholder since Nov 14th, when I bought at 44 with the intention of making a quick 15-20% flip for extra Xmas cash. Oh well.

      1. Plus the negative 32 cents was in a pre-feasibility study which can be up to 30% off anyway.

        Also, the price of metals changed drastically between the pre-feasibility and the feasibility, which affected every project out there, not just ours.

        I was just trying to work out the math on a yearly basis of return from the pre-feasibility to the feasibility and based on the difference in values on the metals the feasibility would generate $51 million less per year. Over the LOM that would be huge.

        The drop in price of molybdenum almost single-handedly accounts for that loss per year.

        Add to that the lower recoveries in the FS, from the pre-FS. We went from 88% copper, 82% gold, 72% silver and 71% moly to 86.6% copper, 73% gold, 48.3% silver and 58.8% moly. So not only was moly half the price by the time of the FS but also had a significantly lower recovery rate.

        The biggest difference, of course, was losing so much material in the pit design.

        1. Re: ....Also, the price of metals changed drastically between the pre-feasibility and the feasibility, which affected every project out there, not just ours.

          To me, generally the PFS had LOWER metal prices than the BFS and and compared to current prices. Molyddenum is the exception.

          The PFS - which had the negative 32 cents. Based on:

          Copper: $3.12/lb (Currently $3.17/lb) (BFS used $3.25/lb)

          Gold: $692.90 /oz (Currently $1,305/oz) (BFS used $1,445/oz)

          Silver: $13.09/oz (Currently $20.00/oz) (BFS used $27.74/oz)

          Molybdenum: $33.00/lb (Currently $13.50) (BFS used $14.64)

          http://www.copperfoxmetals.com/i/pdf/cuu-presentation-sep2011.pdf

          My point is that the metal prices should not have made our economics worst between the PFS and BFS. In fact, using the numbers at the time of the BFS, we should have been even better than negative 0.32. It shows how much the other things pushed up our cost to produce a pound of copper.

          So I'm still expecting/hoping that with the improvements as Prospekt has discussed we will be back in the negative copper costs numbers.

          1. I looked at the metal prices and calculated using the same amount of material shown in the PFS with both prices. It's not just the price of metals it is the ratio of the different metals. That's why the price of molybdenum suddenly became important.

            In the PFS there were 11.3 million pounds of molybdenum produced per year. So in the PFS that amounted to $372.9 million. In the FS it amounts to $165,432,000. That's a revenue loss of $207,468,000. (On top of that we don't have as much molybdenum in the FS, and I didn't even calculate that.)

            Even if you calculate the value of all the other metals that increases in value with the FS, we are still short $51 million a year because of the huge hit we took on moly, and the weight it has on our numbers.

            In the PFS Molybdenum represented 50% of our salable product.