I discovered today that a technical report can be filed by Copper Fox without an independent Qualified Person because the report is being prepared through a JV with a Producing Issuer. Teck is a Producing Issuer because they have revenues of both $30 million in the past year, and $90 million over the past three years.

Here's the clause from the 43-101 regulations:

(4) Despite subsection (1), a technical report required to be filed by an issuer

concerning a property which is or will be the subject of a joint venture with a

producing issuer is not required to be prepared by or under the supervision of an

independent qualified person, if the qualified person preparing or supervising the

preparation of the report relies on scientific and technical information prepared

by or under the supervision of a qualified person that is an employee or consultant

of the producing issuer.

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. Another thought...Teck would be able then to upgrade the waste-that-is-not-waste for us as well. Although, by the same consideration we might not ever hear about it (until, fingers crossed, we have Teck shares.)

    Does anybody have the math handy that calculates the value of the FS if you include the 171 Mt of waste as reserves?

    1. "Does anybody have the math handy that calculates the value of the FS if you include the 171 Mt of waste as reserves?"

      I think one of the main points on this was having it classified as waste. The big cost was not that it was worthless but they had to include the price for complete removal of that 171Mt. It really skewed things and since "inferred" is not allowed in a BFS, why did they not drill it? The drills were there and they were removed three times without doing anything. They were drilling holes in areas that had nothing to do with the BFS but could have done a better job if they just concentrated on the area that they were supposed to be working on. Before it got too foggy for drill crews.....

      Here is my idea:

      All those claims made and delivered to Teck along with the port reservation were at the request of Teck.

      Haphazzard drilling in locations that had nothing to do with, or out of the area of the BFS was ordered by Teck. Otherwise, why waste your time when you could have easily proven the inferred?

      A drilling plan that was announced and 50% was never completed even though we got a news release saying it was successful, well, I'm not sure about that one...

      I hope we hear something on Sept 5th.

      1. "A drilling plan that was announced and 50% was never completed even though we got a news release saying it was successful, well, I'm not sure about that one..."

        Can you explain this a little bit...?

        1. If i recall correctly the last drill program was to be for ~10000m and they only drilled ~3300m.

          It was called successful because they had deemed it was enough for what they required it for.

        2. "Can you explain this a little bit...?"

          They announced a drill program and told us what was to take place. On completion they put out a news release announcing a "successful" drill program but if you looked at it, it turned out that over half of their announced drilling never took place. They explained nothing as usual leaving shareholders with more questions than answers (as usual) so the share price dropped once again. All the questions and related BS could have been avoided if they actually explained themselves in their news releases instead of putting out garbage that leaves shareholders with that blank thousand yard stare. BFS day was a good example of that. They could have stated that copper costs went from negative to $1.15 a lb because of the inferred being classified as waste plus ficticious removal costs but didn't bother so the share price collapsed. Over 90% of the news releases in the last 3 years have dropped the share price. They come out with some line, you read it then go back looking through older material produced by them and figure that this just isn't possible. And it isn't....

          1. They could have stated that copper costs went from negative to $1.15 a lb because of the inferred being classified as waste plus ficticious removal costs but didn't bother so the share price collapsed.

            I don't believe they could have stated things in just this way because of the 43-101 regulations. They can't offer a nudge and a wink and say that really the cost is $.60 a pound or whatever.

            They did say this, The Feasibility Study recommends diamond drilling to determine the extent to which the 171.16 million tonnes of inferred resource that lie within the proposed open pit, now treated as waste, can be upgraded to either a Measured or Indicated Mineral Resource. If successful, this would categorize this rock as a revenue generator.

            They also said this, Within the pit shell there is a total of 171.16 million tonnes of inferred resource grading 0.25% copper, 0.018% molybdenum, 0.164 grams per tonne ('gpt') gold and 1.58 gpt silver which for purposes of this study must be treated as waste rock;

            They also said this, ...Copper Fox undertakes a diamond drilling program at Schaft Creek with a goal to determine the extent to which the 171.16 million tonnes of inferred resource, that lie within the pit shell, can be upgraded to a Measured or Indicated Resource. To the degree such a program is successful it will remove the affected material from being categorized as a rock removal expense to an ore bearing material and as such, a revenue generator;

            I think they did say it over and over again but the only statements they made that counted were the bottom-line figures.

              1. Replying to @Foxyroller

                And it was those bottom- line figures that led to this...

                I doubt it was the bottom-line figures that made Teck back into the project, I would think it was despite those bottom-line figures they backed into the project. Obviously Teck has their own idea of the value of SC.

                1. Replying to @Prospekt

                  The FS was just a necessary step along the way by an explorer tasked to do the deed and further the project development timeline before turning it back over and into Teck's waiting hands. The payback for this was a 25% interest in the project should it proceed. Teck's true interest in SC and surrounding area was clear years before they were formally handed the FS documents.
            1. Replying to @Prospekt

              They also said this, Within the pit shell there is a total of 171.16 million tonnes of inferred resource grading 0.25% copper, 0.018% molybdenum, 0.164 grams per tonne ('gpt') gold and 1.58 gpt silver which for purposes of this study must be treated as waste rock;

              The 171.16 million tonnes of inferred resource has been drilled in the past by Teck and then it was drilled a second time by Copper Fox.

              The total amount of inferred resource is 597 million tonnes grading 0.22% copper.

              1. Replying to @Riskkee

                Evening Riskee

                "The 171.16 million tonnes of inferred resource has been drilled in the past by Teck and then it was drilled a second time by Copper Fox."

                If this was drilled by Copper Fox why was it listed as inferred which then would have been classified (and was) as waste on the BFS? I know this had something to do with the repeated setting up and removal of the drill but it seemed like a small cost to get even close to the professed negative copper cost. When the BFS did come out and showed costs at a buck-fifteen the panic was on and it seems to me it would have been simple to avoid. Or explain...

                1. Replying to @CanadaGrant

                  If this was drilled by Copper Fox why was it listed as inferred which then would have been classified (and was) as waste on the BFS? I know this had something to do with the repeated setting up and removal of the drill but it seemed like a small cost to get even close to the professed negative copper cost. When the BFS did come out and showed costs at a buck-fifteen the panic was on and it seems to me it would have been simple to avoid. Or explain...

                  I not sure but I think your getting warm.

                  Copper Fox drilled the waste for the PFS not the BFS.

                  1. Replying to @Riskkee

                    "Copper Fox drilled the waste for the PFS not the BFS."

                    I was under the impression that Teck drilled it years ago and that Copper Fox hemmed and hawwed about doing it hence the installation and removal of the drill multiple times.

                    My impression is the CUU management already had some sort of a deal with Teck and China and just decided or were told to stop. That would be the reason for the fog. Ever seen a driller that can't work on a foggy morning....?

                    If they did actually drill it for the PFS why would the results not be applicable to the BFS? Drilling in the same spot twice shouldn't be a requirement with the same company doing it.

                    1. Replying to @CanadaGrant

                      If they did actually drill it for the PFS why would the results not be applicable to the BFS? Drilling in the same spot twice shouldn't be a requirement with the same company doing it.

                      It's not the drilling in the waste that matters.

                      The inferred was lost to waste when they did the mine pit design. It was the technical drills at the top on the east side that Teck did last year that would be used to open up the top of the pit, and then allow the mine to go deeper where the waste is located. The technical drills showed how stable the pit wall would be under a new design. Also, the drills to the west.

                      Copper Fox didn't find out until the mine plan was made that they would lose all that inferred. By then it was too late to start drilling again.

                      They could have drilled for one more season and put off the FS for another year after, all the while there was no money and further dilution would have been necessary.

                      Instead they finished the FS that was good enough to trigger the contract with Teck and get some money. It was a judgment call but I think it worked out for the best.

                      1. Replying to @Prospekt

                        Thanks for the great info Prospekt. I was told by a Teck employee that before CUU took this over that Teck had done some limited drilling there and the reason he knew this was that the cores were asked for and being brought out of storage. I posted this quite a long time ago and figured this was the reason for the "multiple" drill pulls.

                        My opinion is that for some reason, they dummied this whole thing down and the lack of any sort of company information on Schaft Creek doesn't help much.

                        1. Replying to @CanadaGrant

                          I phoned the office once and had them read sections of the report on the pit design to me so I could try and understand what was happening.

                          All I remember is that the optimum slope for those ledges (?) are at an angle of 27 degrees. Apparently the east slope is naturally at that same angle and that limited how the mine pit was designed.

                          Teck did some technical drills up there to check on the stability of the rock and were pleased. Why they were pleased, I'm not exactly sure, but if they are pleased, then I am too.

                          Getting this waste included doesn't just convert waste to revenue, but also adds decades to the mine life.

                      2. Replying to @Prospekt

                        Worked out for the best? We're at .21. It was the crap numbers in the fs that triggered our spiral. It lost shareholder confidence and showed a project barely feasible. There were so many delays it created so much anticipation of a great fs and why it tanked. Should have stayed consistent and missed the deadline to have better numbers. Would we be back at .21 I doubt it. It was the one deadline they should have missed. At .21 we will never see a fair offer. The market thinks this is a dog and lost any interest long ago. It's set us up for Teck to get us for a song. I say offer if it comes is under .50. They will never pay what we are truly worth with the sp where it is.
                        1. Replying to @bigbuck

                          "The market"? To whom do you refer? Large brokerages looking to get in on a financing? Nope. They haven't been invited. Ever. Day traders? Nope. Not with so little volume and no hyped NRs from Elmer. Ever. This is a heavily insider owned publicly traded company. We are not susceptible to a low ball offer nor to further dilution. The SP? An acceptable offer won't be based on a premium to the SP. I have heard both Elmer and Ernesto say that. It will be based on the true value of the asset. That said, the SP can be moved fairly quickly in anticipation of a serious offer to placate those who look at a premium to SP. If you want to see how SP fortunes can suddenly swing in your favour just take a look at another company albeit not in this sector.....KLH. It reached a 52 week high last summer at 2.17 and fell back recently into the 60's....only to begin the march upwards again this year on relatively little news to hit 2.51 this week. Largely insider held too..financed primarily non brokered PPs and check out who holds the largest position in that firm. His initials are EE. I am just saying that current SP has little relevance except to those selling shares right now....and to those buying too. The SP can be moved back up. It wouldn't take much buying on the open market to do so.
                          1. Replying to @Foxyroller

                            Elmer can say the price is based on pounds in the ground til he's blue in the face. Teck is not saying that. They pay in multiples of share price, like 30% premium. There is no catalyst for moving the sp, even a production decision will likely do very little with the black cloud over this stock and sector. Could EE buy up the float to move it maybe.

                            Having EE has been a blessing and a curse, we should have gone to market for funding many times to get the brokerages on board. They can move the sp.

                            KLH we are not and you're in the wrong sector. Our sector is still deep in a doom and gloom phase and yes a big part of why we're at .21 and won't hold there either I am waiting for .18

                            My average is .91. I am preparing to put in another 40k to bring down my average to .50 because I think it's likely to get back to .50 but not confindent we'll see .91 again. Hope I am wrong. At some point the venture miners need to get their turn again and out of the doghouse. Who knows when that will happen but it always does eventually.

                            I think we still have 12-18 months to go.

                            1. Replying to @bigbuck

                              That's the thing....Señor E can do whatever he wants and whenever he wants to do it....buy shares on the open market unless blacked out of course.....he can say we will sell to someone other than Teck and choose their partner for them....or he can say, following a positive production decision, 'Let's go mining!' And that's both the beauty and the beast of this investment....we are on his schedule in some ways even more so than Teck's. We must trust him to receive true value for the asset or we would have sold and moved on long ago.
                            2. Replying to @bigbuck

                              I agree with a couple of your points. I have a feeling we could be a year or more away from a significant recovery in base metals and the junior market. I think your point about Ernesto and the brokerages is also true.
                              I don't agree about your point about Teck paying multiples of the share price rather than a portion of the resource. At some point the stock price becomes a ridiculous representation of what the resource is worth, that the metal in the ground has to factor into the offering price.
                              Teck knows that, Elmer and Ernesto know that.

                              I've been fortunate a couple of times to have bought junior stocks that sold for 6, 8, or 10 times what their stock price was before a buyout offer. This still a "multiple" of the stock price, but, I think to suggest we'd sell for a 30% premium (26 cents) is very unlikely. I still feel that this company, and several other juniors out there, have the very real potential of being a 10-bagger - that's a premium, but 1000% not 30%. This story has been dragging on a long time, but we're in a much better position than we have ever been, so I can't accept thinking that there's not significant value and potential in this stock.

                          2. Replying to @Foxyroller

                            "This is a heavily insider owned publicly traded company. We are not susceptible to a low ball offer"

                            Well, we already know what Mr Lindsay said publically about companies with higher insider ownership asking prices which Mr Lindsay said they were not willing to pay. Something you need to consider as well. And even though you don't want to believe it, current SP does indeed have relevance.

                            1. Replying to @babybreeze

                              Well until Mr. Lindsay identifies specifically as to whom or what he was referring to when he said that, it has no direct relationship to CUU or SC. And not to forget this....some here tend to believe Teck will be our buyer and some do not. Either Teck buys us and gets to choose their own partner or we get to choose their partner for them.....or we go mining with Teck should a positive production decision be made. Lots of options.....Señor E's choice. Not Mr. Lindsay's call as you continue to suggest. Btw Mr. Lindsay won't making any decision on SC and/or the purchase of our 25% of Schaft Creek on his own. I believe Mr. Keevil and the BOD will have a significant say in the matter.
                              1. Replying to @Foxyroller

                                You guys are taking this out of context.

                                Question to Don Lindsay was acquisitions in general, what are his views of it?

                                He said companies with large insider ownerships won't sell unless it is a high premium. So basically he's saying they won't or prefer not to acquire an asset that demands a high premium.

                                Well...Teck owns 75% of Schaft Creek already. They are the operator. They acquired a large percentage of the asset already.

                                It is in Teck's favour to acquire our 25% interest because of the financing condition in the JV. If not, Teck doesn't have to buy us out. CUU can easily sit through production and collect $113 million a year after capex is paid back. Or some other big miner/fund can swoop in and buy our interest.

                                Teck/CUU JV relationship is more like Rio Tino and Ivanhoe back in the day. You have a big miner funding the operations and you have the small guy following along. I think their JV was not as advantageous as CUU so we are slightly up on that. (I think Ivanhoe had to issue shares to fund their percentage of the construction??)

                            1. Replying to @ecua

                              I wish I had something to add to this thread, other than to state it has been one of the best discusssions in a long time. Very informative and solidified my thoughts on my position. In till the end.
                          3. Replying to @Foxyroller

                            Good post Foxy. IMO If CUU would be in another sector than mining we could see a lot of speculation and anticipation I believe... Mining is not sexy nowadays and watching our story unfolds will remain, it seems, painful and dull until the pay-day.

  2. I should add that BigBuck said Teck may not be prepared to have their own QP certify the update anyway. It is possible even though usually the QP has to be at arms length.

    It sounds like they don't believe Teck will update the FS, and will jump to the production decision (and maybe make us an offer prior to that point depending on who you speak with. Cathy says after production decision, Elmer has said before.)