Once the remodel is done, sometime in April although CUU has retained AMEC to review the results and we don't know how long they will take, a decision will be made to keep the existing resource estimate or update it. Obviously this is a major decision which could trigger one of two paths. If an update is not required then Teck should be in a position to accept, finally, the resource and reserve numbers and book them on their balance sheet.  That should be sufficient for CUU to put SC on the market for sale and monetize the asset. If an update is required then we need to know how much work and how long that will take. 

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. Good morning EG. My question is how, as a minority owner of Schaft Creek does CUU go about monetizing anything when Teck has never stated their intentions towards a timeline or even if, let alone when a mine is to be built in the future?

    How would they find a buyer when you have no idea what you are selling? Teck barely acknowledges Schaft Creek is even there let alone any sort of timeline or plan for it. So, here we sit....

    1. The outcome of the resource remodel will address your points although an RE redo will take longer. I agree that CUU has nothing to sell at SC until Teck agrees on the resource estimate. Until that happens neither Teck nor anyone else has a number to calculate a value. You can sell a mineral asset at any stage of development, you just get less for it depending on the amount of de-risking. 

  2. Remodelling Announcement from March 30, 2016:  

    "This aspect of the 2016 work program includes incorporating the work completed in 2014 and 2015 to update the resource model for the Schaft Creek deposit. This phase of the program will emphasize getting a better understanding of the precious metals content of the deposit."

    Remodelling Annoucement from February 2, 2017:

    "The work to complete the remodel of the Schaft Creek resource is progressing. This work was expected to be completed by the end of the first quarter, but due to technical issues related to the complexity of the database the completion date has been extended by several weeks."

    It's very hard to get any kind of accurate timeline.     Get it sold and let the investors move on.

    Thank you!

     

    1. Teck has complete control of the timeline to deliver the SC work and no pressure from their investors to do anything in particular with SC.  The remodel work completes the review of the FS elements that's taken 3 years. We're going to find out this year if that effort results in an outcome that ranges from something good(asset sale) to something very bad(complete redo of the FS). 

      1. Sounds good.   I just want to see it "monetized" now, which has been a word we've been using around Schaft Creek for a long time.   Yes, I don't want to pressure anything.   I just want to get off the bus with something close to my shirt in tact.   Not bashing the company, just want off the bus.  Modeling, remodeling, prefeasibility, feasibility, relogging, reviewing, etc.

        By the way, where are the optimization studies which began in 2014, carried on into 2015?   Does it take 3+ years to do the optimization?  

        Where is the optimization report?

        1. The optimization and resource re-modeling work appears to be part of a compete rework of the FS by Teck. The next areas they are reworking are the metal prices, FOREX, OPEX and CAPEX. After that the only thing left is to calculate the RE, so I expect they will proceed with it.