Based on my calculation, reducing the construction timeline by 1 year and increasing the free cash flows by 25% doubles the PEA NPV (8%) @ $3.25 copper, $1500 gold, $10 moly.

@ $4.00 copper, $1800 gold, $15 moly that adds another $1.3B US per the tornado charts.

If Teck estimates building Galore in 5 years with permitting and engineering, 4 years for SC should be possible?

If Teck estimates a $0.50 US C1 cost (LOM) vs. our PEA $1.00 US C1 cost (LOM), increasing the free cash flows by 25% is a reasonable assumption?

Small changes = big impact.

Do the math.  I'm at $3B US.