2024 SC program news from a year ago! It's the same objective!
2024 Program Highlights:
The objective of the program is to advance the key project parameters to transition the project from Scoping to Prefeasibility Study (“PFS”) stage by the end of 2024 or early in 2025.
Planned expenditures in 2024 are C$18.7 million to be fully funded by Teck.
Technical Activities:
Completion of the metallurgical testwork program currently underway
4,500m of drilling focused on key technical areas including the Highwall, Tailing Storage Facility (“TSF”), and Rock Storage Facility (“RSF”)
Engineering Studies:
Site wide geotechnical and facilities assessment of the TSF, RSF and proposed infrastructure
Update access road alignment
Update construction timeline
Updates to the Resource, Geologic, Structural and Slope Stability Models
Continue the Environmental Baseline data collection program initiated in 2023 and strengthen collaboration and engagement with the Tahltan Nation.
Pre-Production Costs at Schaft Creek have exceeded $60 million as set out in the SCJVA.
The primary objective of the 2025 program is to transition the project from the Scoping stage to the Preliminary Feasibility Study stage (PFS).
Planned expenditures in 2025 are C$15.8 million shared pro-rata by Teck and Copper Fox.
Main components of the 2025 program include: Technical
Review of current technical models and updating as required
Completion of Geometallurgical Program including interpretation and modeling of data
Completion of Geotechnical Slope Stability and Hydrogeological Models
Trade-off Studies on potential infrastructure sites
Field Program
Environmental Baseline data collection
Archaeological investigations in key site infrastructure locations
Drill program to assess suitability of planned site infrastructure
Sooooo does this mean we need to spend 25% of 15.8 Million? Clearly we don't have that... Couldn't probably get 50% of that in a pp... So now we are going into debt with Teck? What in the actual F is the board thinking...
Yes we'd be on the hook for the 25% but I think that teck pays and then it's deducted off when the mine goes into production so we do not need to put up the money up front. I recall it was talked about here extensively a while ago and maybe somebody can give is some of the agreement details
Before a debt is incurred (which is later repaid from CUU's 25% of earnings), the SCJV "project sanction announcement" bonus of $20 million for CUU gets eaten away at the rate of 25% of total expenses inccurred above the (already blown away for next-to-nothing in return) first $60 million which is 100% on Teck's tab.
So if Teck spends from here $80 million then our $20 million sanction bonus is pre-eaten up. Then after that, on the same 75/25 basis Teck starts to eat away at our last and final $20 million bonus on 'First Production".
Based on Teck's last 12 years as a lame operator with a jr-starvation strategy they will probably shoot for that water drip torture strategy over the next few decades eating away at our bonuses, despite this insanity meaning that Teck will forego 75% of a billion plus in annual revenues from Schaft Creek.
No we don't pay anything . It will be deducted from the 2 x 20 million dollar milestone payments. Teck would need to spend another $80 million to exhaust our $20 million milestone payment. Teck will piss away all of 2025.