And before that the 2015 PEA took 9 months
The 2015 Preliminary Economic Assessment (PEA) for the Van Dyke In-Situ Copper Recovery (ISCR) project in Arizona was conducted by Copper Fox Metals Inc.
The engineering and technical studies leading up to the report took approximately 9 months of active development, culminatig in the full technical report published in May 2015.
Timeline & Key Milestones
August 2014 — Project Kick-Off: Copper Fox engaged Tetra Tech Inc. to manage and prepare the PEA, alongside specialized hydrogeological and mining sub-consultants (including Sparkes Geological Services and Ausenco).
November 2014 — Resource Estimate: An updated mineral resource estimate was completed, establishing the foundational data needed for mine planning, wellfield design, and recovery modeling.
November 2014 to March 2015 — Metallurgical & Engineering Studies: Design of the wellfield layout, solvent extraction-electrowinning (SX-EW) processing plant facilities, and hydrogeological modeling were finalized.
November 25, 2014 — Initial PEA Results Released: Copper Fox announced the preliminary economic results via press release.
May 7, 2015 — Final Technical Report Filed: The formal NI 43-101 Technical Report detailing the PEA was officially completed and filed on SEDAR.
Key Parameters of the 2015 PEA Plan