Down the road from us
Some info from Trekor’s recent presentation...
herbie1
By investing.com
Florence copper mine
Florence is Trekor’s growth asset and the main reason management expects cash generation to improve sharply over time. The Arizona mine began producing copper cathodes in February 2026 after a long permitting process and a construction phase that started in 2025.
- Location: Arizona
- Acquired: 2014
- Permitting period: about 10 years, with final permits received in 2023
- First copper cathode production: February 2026
- Q1 2026 production: 1.5 million pounds
- Q2 2026 production: 5.2 million pounds
- 2026 guidance: 30 million to 35 million pounds
- 2027 target: 80 million to 85 million pounds
- Mine life: 22 years
Management said Florence uses in-situ recovery, or ISR, a method that avoids conventional mining and earthmoving. The process relies on injection and recovery wells that circulate a copper-leaching solution through the ore body. Trekor said it ran a production test facility for 18 months and produced 1 million pounds of copper to validate the process before full construction began.
The company said Florence started with 90 wells in late 2025 and is now drilling about 100 more wells in 2026, with similar annual well-field expansion expected for the rest of the mine life. Trekor said Florence should become cash flow positive within about a month of the presentation date.
At full capacity, Florence is expected to produce 80 million to 85 million pounds of copper a year at cash costs of about CAD 1.10 a pound, roughly 54% lower than Gibraltar. Management said the mine should produce 99.99% pure copper cathodes, a finished product that does not need further refining before moving to a rod mill.
Trekor also pointed to the project’s valuation potential. Management said Florence has an estimated net present value of about $1 billion at $3.75 copper and more than $2 billion at $6 copper.
Several of management’s remarks centered on the company’s North American focus and Florence’s economics.
- “We are the only copper producer that is solely North American. All of our peers have exposure to other areas such as South America and Africa, but we have made the choice to stay in North America, a nice, secure political jurisdiction.”
- “Our Q2 earnings were some of the best earnings we have ever produced. We did CAD 330 million of revenue, CAD 125 million of Adjusted EBITDA, and CAD 180 million of cash flow.”
- “Florence, once we ramp it up, it will produce 85 million pounds of copper per year. Again, a very long mine life at 22 years. Cash costs here are much lower. We expect we will be able to produce at about CAD 1.10 per pound once it is fully ramped up. About half of what Gibraltar is.”
- “At $3.75 copper, Florence has got nearly a billion-dollar U.S. NPV. At $6, a little lower than where it is at today, that NPV jumps to over $2 billion. This is a fantastic asset and is going to generate a lot of cash for us.”
Conclusion
Trekor said its near-term focus is on completing Florence’s ramp-up, keeping Gibraltar stable and advancing well-field drilling in Arizona.
Readers can refer to the full transcript below for more detail from the conference call.
Full transcript - Lytham Partners Fall 2026 Investor Conference:
Join the conversation about Copper Fox Metals Inc.
Reply