Electra Battery Materials Corporation
TSXV:ELBM
Electra Battery Materials Corporation is a Toronto-based critical minerals processing company.
Company facts
- Exchange
- TSX-V
- Symbol
- ELBM
- Industry
- Metals & Minerals
- Website
- electrabmc.com
Company overview
Electra Battery Materials Corporation
Electra is recommissioning a battery-grade cobalt sulfate refinery.
Permitted refinery in Ontario, Canada.100% cobalt feed secured through 2027.Commercial output targeted Q4 2027.
Electra Battery Materials Corporation is a Toronto-based critical minerals processing company. Its main asset is a permitted brownfield hydrometallurgical refinery in Ontario being recommissioned and expanded to produce battery-grade cobalt sulfate. The company is pre-revenue and in construction, with commercial production targeted for Q4 2027.
- C$23.5M
- Cash on hand
- C$82.8M
- Avail. funding
- C$100M
- Refinery budget
- 100%
- Feed secured
TSXV: ELBM | Nasdaq: ELBM
Pre-revenue critical minerals processing company.
A permitted Ontario cobalt refinery.
- Permitted brownfield hydrometallurgical refinery in Temiskaming Shores, Ontario.
- Initial capacity of 5,120 tonnes per annum of contained cobalt.
- 100% cobalt hydroxide feed secured through 2027 under Glencore agreement.
The company is pre-revenue and in construction, with commercial production targeted for Q4 2027. It also owns the Iron Creek project and studies a nickel refinery and black mass recycling.
Cobalt, nickel and recycling assets.
Portfolio of three projects.
Ontario
Ontario Cobalt Sulfate Refinery
Permitted brownfield refinery being recommissioned for battery-grade cobalt sulfate. Initial capacity 5,120 tpa contained cobalt, with board-approved budget of C$100M (US$73M); 46M construction packages awarded.
Idaho
Iron Creek cobalt-copper project, Idaho
Indicated resource of 4.4M tonnes grading 0.19% cobalt and 0.73% copper; not yet demonstrated economic viability.
Proposed
Proposed nickel refinery and black mass recycling
Two-phase U.S. nickel refinery concept; Phase 1 evaluates 20,000 tpa contained nickel as battery-grade nickel sulfate, estimated capital US$530M–US$675M.
Financial position as of September 30, 2026.
Financial and share data.
Key balance sheet and capital figures.
C$23.5M
Cash and cash equivalents as of September 30, 2026.
C$82.8M
Available cash and project funding, including remaining government reimbursements, as of September 30, 2026.
C$42.6M
Term loan carrying value as of September 30, 2026.
107.0M
Common shares outstanding as of November 6, 2026, plus 26.4M pre-funded warrants.
All figures in Canadian dollars; period end September 30, 2026 unless noted.
Key announcements and milestones.
Recent milestones
- Nov 2026
- Q3 2026 results reported. Approximately C$46M of construction contracts committed against the C$100M refinery budget; C$82.8M in cash and undrawn government funding at September 30, 2026.
Oct 2026
- WMC Group AG term sheet. Non-binding term sheet for five-year working-capital and commercial partnership covering cobalt feedstock finance, logistics and marketing; WMC to invest upon definitive agreements.
Aug 2026
- Glencore feed extension. Cobalt hydroxide feed purchase agreement extended through December 31, 2031, covering 100% of feedstock for commissioning and ramp-up through 2027.
May 2026
- C$25M construction package. Awarded to WB Melback Corporation to complete the solvent extraction building at the cobalt sulfate refinery.
May 2026
- Government of Canada investment agreement. Definitive investment agreement under the Strategic Response Fund for C$20M toward eligible refinery project costs.
Mar 2026
- LG Energy Solution supply update. Updated multi-year supply agreement committing approximately 60% of planned cobalt sulfate production through 2029.
Planned path to commercial production.
Upcoming milestones
Q4 2026
- Early commissioning. Select utilities and circuits at the Ontario refinery planned for early commissioning.Planned
Q2 2027
- Mechanical completion. Mechanical completion of the Ontario cobalt sulfate refinery planned.Planned
Q3 2027
- Ramp-up begins. Ramp-up of the refinery planned to begin.Planned
Q4 2027
- Commercial production. Commercial production targeted for Q4 2027.Planned
TBD
- WMC definitive agreements. Finalize definitive agreements with WMC Group AG, subject to due diligence, documentation and approvals.Planned
TBD
- Nickel refinery study. Site assessment, permitting, funding, feedstock and offtake discussions, and further engineering toward a FEL-3 study.Planned
Key risks and disclosures
- Going concern: additional capital required for operations and construction.
- Nasdaq minimum bid price compliance required by March 15, 2027.
- WMC term sheet non-binding; subject to due diligence and approvals.
Who runs the company
- Trent Mell, Chief Executive Officer
- Peter Rawlins, Chief Financial Officer (effective August 26, 2026)
Unclaimed AGORACOM Hub. AGORACOM wrote this overview from the company’s public filings, news releases and website. The company is not an AGORACOM client and has not reviewed it. It is not investment advice.