Question for any experts...

seeing that we do start at surface, is it not possible to start mining relatively quickly and have the ore processed at another location, which might not be too far away, to extract the Gold. Therefore, no need to immediately set-up a processing plant and use the profits for continued exploration? Thereby minimizing dilution of shares.

Skier

Join the conversation about Golden Hope Mines.

Reply

Replies

  1. Just doing some very quick simple math,

    it costs about $4.50 per tonne to load and haul aggregate provided that it is close and you can maintain a fast turn around. The aggregate must be fine enough (12mm minus) so you don't tear the truck apart. A back-haul is unlikely. If you have about 1g/t then your cost just to truck rock would be more than 10% of your retail value provided gold stays above 1300.00.

    You would also need a road system capable of handling heavy load traffic year round. You would need to have a mill less than 15-20 kilometers away and an assay value over 3g/t to even consider hauling rocks around the countryside imo.

    However, I'm no expert in mining or gold production but I did own dump trucks and I know how expensive it is to haul anything with on-highway trucks. If you have a mill within the distance and infrastructure requirements of a fleet of F797 Caterpillar off-road trucks then maybe yes.

    jmo..........carry

  2. Skier -

    I recently read of another company that was selling their bulk sample. That seems like a good way to generate cash.

    Can GNH do that?

    - panamax

    1. Sorry, I thought skier was asking about actually mining, not selling the product of our bulk sampling protocol.

      I suppose it would be interesting to know what happens to the gold that is recovered from a bulk sample?

      anyone know?

      .........carry

      1. No, PCarry you were correct, I was thinking of trying to go down 50m or so, but you answered my question on that subject, Thanks

      2. When we were on the site visit we saw all of the sacs of the pulverized material from the 2009 bulk sampling in the warehouse/processing facility. Theoretically that could be sent away for processing as could the crushed rock piles from the field of dreams but I think the company will need to keep all of them around at least until all compliance issues with respect to a resource estimate are met and documented by a third party qualified person. My understanding was that Jim Tilsley may also be able to use some of that pulverized material for determining the gold grain size distribution - a helpful step in defining accurate grade estimators. I believe the gold that goes into the assays themselves is destroyed as part of the measurement.

        Best,

        Scott