First Canadian ferrochrome produced from ROF
http://xpscentre.ca/EN/Publications/Publications/XPS%20News%20Release_2012-02-07%20-%201st%20Can%20Ferrochrome%20from%20DC%20Furnace.pdf
Join the conversation about The Canadian Chrome Company Inc.
ReplyYou’re reading chauncey gardiner’s reply in this thread.Jump to it
http://xpscentre.ca/EN/Publications/Publications/XPS%20News%20Release_2012-02-07%20-%201st%20Can%20Ferrochrome%20from%20DC%20Furnace.pdf
Join the conversation about The Canadian Chrome Company Inc.
Reply.
Great find "Chauncey Gardiner" its a great report from Xstrata, the only thing missing from the report is the % of recovery and the ferrochrome alloy grades.
I'm sure when they do the bulk sample test work of the "Big Daddy" we will get that infomation from KWG Resources.
.
.......RL
Hi "Rocklicker"
RE: ...the only thing missing from the report is the % of recovery and the ferrochrome alloy grades. I'm sure when they do the bulk sample test work of the "Big Daddy" we will get that infomation from KWG Resources.
Yes, it will be nice to get that info. It may shed a better light on Cliffs intentions as to which deposit they will move forward on first.
And that bulk sample test just might already be underway.
From the Jan. 24 news release;
Metallurgical Drilling - The metallurgical drilling program was to consist of 1,900m of HQ drilling. The program commenced on October 6, 2011 with one drill rig, with a second rig added on October 11, 2011. The total completed meterage was 1,909m in nine (9) boreholes and was concluded on October 22. A bulk sample consisting of massive chomitite with a mass of 4,600kg was removed from core boxes and packaged for transport to Xstrata Process Support (XPS) in Falconbridge, Ontario. The furnace runs are scheduled for February.
Better to have the most economically viable results than to be just the first. Since the news release mentions completion on, I think 3rd February, KWGs bulk sample will be processed after that 'during February'. CLF will compare both deposits carefully before making any decisions, and if there is a significant difference, we may come out winners.
Another factor to consider is their first step will be to mine and ship ore that does not need enrichment, in order to get cash flow while building the smelter. That of course requires transport infrastructure.
Here are the link for KWG NR on 24 Jan 2012 and its full text (at end of meaasge) for future reference.
The following items are worth noting
- It was a KWG (not CLF) News Release, and it was for Big Daddy
- There are 2 types of drilling mentioned in that NR:
(a) Met Drilling: This was to provide the 4600 kg of the bulk samples for the furnace runs scheduled for Feb 2012. Today is 20 Feb 2012, so there are 9 days left, if there is no delay.
(b) Resource Delineation Drilling: To outline the best (most profitable) contour of the open pit. 23 out of 38 holes (more than half) have been completed before 15 December 2011. Complete of the rest is anticipate for the 3rd week of Feb 2012 (not 3rd Feb). Perhaps, I am reading too much into this timing, but there must be something significant about 1 April?
Agreed that KWG holds two aces: one is the DSO quality of BD (my guess: they will check this as well using the bulk samples...for confirmation of the grade, in addition to the furnace runs); and two, the RR of course (CLF would need that to get the stuff out regardless of the choice between BT or BD. I would bet on BD to be the first).
goldhunnter
--------------------
http://www.kwgresources.com/news/index.php?&content_id=307
Montreal, Canada – January 24, 2012 – KWG Resources Inc. (TSXV: KWG) is pleased to provide an update with regards to the current field program on the Big Daddy Chromite deposit.
Metallurgical Drilling - The metallurgical drilling program was to consist of 1,900m of HQ drilling. The program commenced on October 6, 2011 with one drill rig, with a second rig added on October 11, 2011. The total completed meterage was 1,909m in nine (9) boreholes and was concluded on October 22. A bulk sample consisting of massive chomitite with a mass of 4,600kg was removed from core boxes and packaged for transport to Xstrata Process Support (XPS) in Falconbridge, Ontario. The furnace runs are scheduled for February.
Resource Delineation Drilling - The resource delineation program was to consist of 12,000m of NQ drilling in 38 boreholes. Drilling started immediately following the completion of the metallurgical sampling holes as the rigs became available and was carried out continuously with two rigs until winter shut down on December 15. In that time 23 of the 38 holes were completed for an aggregate total of 7,754m. Completion of the drilling is anticipated in the third week of February.
About KWG: KWG has a 28% interest in the Big Daddy deposit and is presently earning an additional 2% interest in it under an option agreement to create a joint venture with Cliffs Natural Resources Inc. (Project Operator) on April 1, 2012. KWG also owns 100% of Canada Chrome Corporation which has staked claims and conducted a $15 million surveying and soil testing program for the engineering and construction of a railroad to the Ring of Fire from Exton, Ontario where the Trans Canada line of the Canadian National Railway can be connected.
For further information, please contact:
Bruce Hodgman
Vice-President
416-642-3575
[email protected]
Follow Us On:
Facebook: http://www.facebook.com/kwgresourcesinc
Twitter: http://twitter.com/kwgresources
YouTube: http://www.youtube.com/KWGresources
Flickr: http://www.flickr.com/photos/kwgresources
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Replying to @lowboy
Lowboy, you are correct, there have been two relevant News Releases about smelting ROF chromite bulk samples. The first, from KWG, relates to Big Daddy ore and is scheduled for 'February'. The second, more recent NR, relates to ore supplied by CLF apparently from Black Thor, and the first pour was 1st February, so the actual work began before February and continued after Feb 1st.
Here is the text of the more recent NR
Successful First Tap of Ferrochrome from Ring of Fire ‘Black Thor’ Chromite Deposit at XPS facility using a new DC Pilot Test Furnace
On the morning of February 1, 2012, the first ferrochrome alloy was tapped from a new DC pilot test furnace at the Xstrata Process Support (XPS) Centre (www.myxps.ca), in Falconbridge, Ontario.
This is the very first continuous smelting of ‘Ring of Fire’ chromite ore in Canada‛, says Arthur Barnes, Consulting Metallurgist, XPS.
The ore tested is from the ‘Black Thor’ deposit, and the work is being performed under contract for Cliffs Natural Resources (www.cliffsnaturalresources.com), who through its Canadian subsidiary, Cliffs Chromite Ontario Inc., is the owner and currently developing the deposit located in the James Bay Lowlands of Northern Ontario.
Cliffs is excited about developing this smelting test capability in Canada instead of having to ship samples overseas‛, stated Richard Fink, Cliffs’ Vice-President – Technology, Global Ferroalloys.
The experienced team at XPS is working closely with Cliffs to test the ore using best practice processing and environmentally sustainable technology to further define and validate the design parameters for Cliffs’ full scale plant.
‚This is a positive development in the story of Chromite in Canada‛, says Arthur Barnes, ‚and we are proud to be supporting this exciting work for Cliffs with our experienced team at XPS.‛
With the support of Cliffs, the pilot scale furnace is now fully operational and producing larger scale test results. This complements similar work already underway for furnace design, commissioning, training and operation.
‚Congratulations to our dedicated team at XPS for achieving this milestone, safely, without any major incident‛, says Dominic Fragomeni, Director at XPS. ‚We look forward to continuing our support of Cliffs in the development of this significant deposit for Northern Ontario and Canada.‛
I assume that after completion of the tests on B.T. ore, the same tests will be done on B.D. ore, so that a full comparison can be made.
They will try different methods to find the best - temperatures, flux, particle size etc
CLF will want to know about both orebodies before deciding where to mine.