Press Releases - Tuesday, November 18, 2008

Re: Press Releases - Tuesday, November 18, 2008
Palladon Iron Corporation Acquires additional 2,000 Acres of
Mineral Property at Iron Mountain, Utah
====================================...

Salt Lake City, Utah, November 18, 2008. Palladon Ventures Ltd.
("Palladon" or the "Company") (TSX.V: PLL) (Frankfurt: PV-1) through its subsidiary, Palladon Iron Corporation ("PIC"), acquired an additional 2,200 acres of mineral rights on the north side of Iron Mountain at its iron project, located approximately 20 miles west of Cedar City in southwestern Utah. PIC staked 111 lode mining claims to cover a series of magnetic anomalies defined by a recently completed aerial magnetic survey contracted by the Company. These new claims expand PIC's property position by over 30% to over 8,500 net mineral and surface acres of mining property.

All the iron deposits in the Iron Mountain area contain magnetite, an ore mineral of iron that produces a significant magnetic response if that mineral is concentrated in sufficient quantities. Palladon contracted an airborne magnetic survey to be flown over Iron Mountain to measure the magnetic response of the known iron deposits and to indicate additional areas where iron deposits might be present. Although the results of that survey are still being evaluated, PIC decided the results of the survey warranted staking the new lode claims. An exploration drilling program is in the planning stage and will be announced when plans are complete.

"We are excited about what our initial interpretation of the magnetic survey tells us. We feel the ground we just acquired has potential, but we won't know the full potential of this area until we have the opportunity to drill it," said Donald G. Foot, Jr., President and CEO of Palladon Ventures Ltd.

On Behalf of the Board of Directors,
Donald G. Foot, Jr.
President & Chief Executive Officer

WARNING: This news release may contain forward-looking statements
including but not limited to comments regarding the timing and content
of up-coming work programs, permitting processes, the first shipment of
iron ore from the site, potential mineral recovery processes, etc.
Forward-looking statements address future events and conditions and
therefore involve inherent risks and uncertainties. Actual results may
differ materially from those currently anticipated in such statements.
Palladon Ventures Ltd. relies upon litigation protection for
forward-looking statements.

The TSX Venture Exchange has not reviewed and does not take
responsibility for the adequacy or accuracy of the contents hereof.

Join the conversation about Palladon Ventures.

Reply

Replies

  1. China's steel makers have cut production due to lower profit margins, and weaker demand at home and abroad. China produced 35.9-million tons of crude steel in October, down -23% from a record high of 47.1-tons in June. Some 90-million tons of iron ore are now stockpiled in Chinese ports, two months worth of imports, due to a sudden collapse in demand by steel mills. Chinese orders for copper, nickel and a range of other base metals have also plummeted.

    1. I talk to management and there will not be an update this week because of the long weekend coming up and problem solving being done at the port. I think that is a crappy excuse for not having an update. But thats what was explained to me.

        1. UPDATE: WEDNESDAY, NOVEMBER 26, 2008

          This update is provided a few days late as we have been traveling extensively to keep this project moving forward with the short week here in the US. We are happy to provide the following on the progress at it’s Palladon Iron Corporation Iron Bull Mining & Milling facility near Cedar City, Utah.

          • Mine site development is progressing according to budget and is currently in operation in respect to mining, crushing and building of the stockpile.

          • On August 31, 2008, the Company had total cash resources of US$13.5M, providing sufficient cash to carry the company into cash flow.

          • The Company has all mine permits in place for operation at 2M, 4M or more tons per year using the run-of-mine scenario.

          • The Company has completed the refurbishment of the 14.6 mile spur line from Iron Mountain to Iron Springs and the rail is operational.

          • Union Pacific rail cars are now on-site and the short-line operator’s engines are currently moving the train cars freely at the site.

          • Rail cars are currently being loaded to calibrate the new tipple system for assurance that the cars do not exceed UP standards for movement of ore.

          • An Aeromagnetic survey was completed at the site that covered the entire Iron Mountain property.

          • The site is ready for shipment once the temporary facility is ready to accept iron ore. The permanent facility is still going through approval.

          • Personnel changes have been made to the staff and Rick Russell is now playing a more significant role as the Acting Chief Geologist.

          IRON MOUNTAIN PROJECT

          The development of the Iron Mountain project has reached new milestones as mining and production were started prior to the end of Q3 2008. The mine is currently operating at 5000 tpd, four days per week to build a 150,000-ton stockpile in anticipation of shipping. The first material was drilled blasted and hauled on September 15, 2008 and crushing was initiated shortly thereafter. Expenditures for start-up were below the budgetary values. The following are highlights of the accomplishments to date at iron Mountain:

          • The first phase of the rail improvement plan was completed from Iron Mountain to Iron Springs and is now operational.

          • Ballast was produced from the tailings dumps with the fine material providing road base for all mining roads

          • The 84 inch horizontal crusher was installed and is currently crushing 5000 tpd of >55% Fe run-of-mine ore.

          • The radial stacker was installed and is successfully blending product to form a 150,000 ton stockpile.

          • The Tipple was erected and is fully operational loading cars in less than two minutes including positioning.

          • The substation was successfully commissioned and is providing power to the entire site and all ancillary facilities.

          • The site is now in full operation with the commencement of drilling, blasting, hauling, crushing, stockpiling and loading.

          SHIPPING

          Shipping has been delayed as tenants in the temporary barn continue to store and ship material. It is anticipated that this will be rectified in the next few weeks. Refurbishment of the barn is necessary to handle the higher density iron ore. This requires that the plows that move the material onto the load-out belt be stiffened and the Tee-Pee system in the center of the barn be reinforced. Engineering has been completed and work will commence once the barn is free of material and clean. We are continually looking at ways to expedite the shipping process and get the iron ore moving as quickly as possible.

          AEROMAGNETIC SURVEY

          An aeromagnetic survey was completed in September 2008 and surveyed some 6000 acres. The results showed that there are significant additional areas of interest and therefore Palladon secured approximately 2200 additional acres of BLM land through staking. This brings the total acreage under control of Palladon Iron to approximately 8500 acres. This represents an increase in holdings of 35 percent.

          The results of the survey will be released once Rick Russell and his staff complete a thorough evaluation.

          Pictures documenting the progress at the mine site can be found at www.ironbullmining.com.

          STAFFING CHANGES

          The Company is pleased to report that Mr. Rick Russell who has served as a qualified person for many years with the Company is now taking a more significant role as its Acting Chief Geologist. Rick will be responsible for all of the geology and geological engineering studies at the site, all land and water issues, and all future exploration work.

          The Company reports that Frank Dolce has left the organization to pursue other career opportunities. His position will be replaced with a transportation and logistics manager.

          We are also pleased to announce that Del Satterthwaite has joined the company as the IT and Communications Manager. Del comes to us after spending the last 20 years with Digital Equipment Corporation, Oracle Corporation, and NetApp.

          We would like to wish all of our US shareholders a very HAPPY THANKSGIVING.

          1. Dec 01/08 Nov 28/08 Etzel, Annjanine Freeman Direct Ownership Common Shares 10 - Acquisition in the public market 500 $0.155
            Dec 01/08 Nov 26/08 Etzel, Annjanine Freeman Direct Ownership Common Shares 10 - Acquisition in the public market 50,000 $0.120
            Nov 21/08 Nov 20/08 FOOT, Jr., DONALD GRAHAM Direct Ownership Common Shares 10 - Acquisition in the public market 20,000 $0.149
            Nov 18/08 Oct 23/08 Clark, Jeffrey D Direct Ownership Common Shares 10 - Acquisition in the public market 20,000 $0.239
            Nov 17/08 Nov 17/08 FOOT, Jr., DONALD GRAHAM Direct Ownership Common Shares 10 - Acquisition in the public market 15,000 $0.213
            Nov 11/08 Nov 05/08 Clark, Jeffrey D Direct Ownership Common Shares 10 - Acquisition in the public market 20,000 $0.258
            Nov 11/08 Nov 04/08 Clark, Jeffrey D Direct Ownership Common Shares 10 - Acquisition in the public market 500 $0.298
            Nov 11/08 Nov 04/08 Clark, Jeffrey D Direct Ownership Common Shares 10 - Acquisition in the public market 2,500 $0.299
            Nov 11/08 Nov 04/08 Clark, Jeffrey D Direct Ownership Common Shares 10 - Acquisition in the public market 17,000 $0.298
            Nov 11/08 Nov 03/08 Clark, Jeffrey D Direct Ownership Common Shares 10 - Acquisition in the public market 4,000 $0.275
            1. Replying to @svosteve

              UPDATE: MONDAY, DECEMBER 1, 2008

              There have been numerous requests to see how the plant and the stockpile look at this moment at the site. Figure 1 shows the plant and stockpile as it sits today.


              Figure 1: Iron Mountain Processing Site

              This is a panoramic view taken from a waste dump just south of the site. The current stockpile holds nearly 150,000 tons of crushed ore ready to load into the rail cars. In front of the stockpile is the red stacker that loads the freshly crushed material. The crusher cannot be seen, but is in the ridge just in front of the stacker. The crushed material is drawn from the bottom of the stockpile on a conveyor that runs inside a tunnel underneath the pile. The conveyor then loads the material onto the larger silver conveyor system that feeds the tipple. The tipple has three individually operated door mechanisms that are computer controlled to ensure an balanced load on all the rail cars. Please note the string of rail cars under the tipple in the process of being loaded. The cars to the left of tipple that pass behind the stockpile are loaded and being stored on the ancillary tracks for shipment.

              This week will be busy at the site with railcar and weigh-scale testing. Officials from the Union Pacific Railroad (UP) and the State of Utah will be onsite to ensure the scale is calibrated properly. A properly calibrated scale will allow us to ensure that we meet the specifications for movement of unit trains on the UP lines and at the port.

              With all this going on at the site, our highest priority is still our work with the port to assure its readiness to receive our ore.

              1. Replying to @svosteve

                UPDATE: MONDAY, DECEMBER 8, 2008

                This past week was busy with calibration of the scale for the railcars and continued mining. Calibration of the scale for the railcars was successful. In the photo below, the Utah Department of Transportation (UDOT) employees are working with the conductor from Utah Southern Railroad as they use the calibration car on the scales.

                The next photo is the inspections certificate signed by the UDOT representative.

                We now have the scales properly calibrated for shipping. UDOT has certified the scale, and the Union Pacific is in agreement. Based on the result of this testing and certification, all the ore we have in the cars is within the specified weight and ready to ship.

                All activities at the mine are progressing well, and as expected. Most of the work right now is moving waste to the waste dump and moving lean ore to the lean ore stockpile for future use. This work allows us to expose more of the resource so we can readily access it as we start shipping and replenishing the stockpile.

                1. Replying to @svosteve

                  UPDATE: MONDAY, DECEMBER 29, 2008

                  There is very little for our update with most companies off for the holidays. We expect the next material update to be on the 12th of January after New Years and when the people we are contacting are back at work. HAPPY NEW YEAR .

                  UPDATE: MONDAY, DECEMBER 22, 2008

                  We are on a short week here with Christmas on Thursday. The mine will be closed for Christmas. It has been very snowy in Utah this week as it has around the country. After a couple of storms we have 8 inches of snow at the mine at this time. We expect winter weather from now until March, but it won't significantly affect mining. Progress at the mine continues as we move lean ore to its stockpile for future use. Waste is being moved daily, exposing more ore. Senior management is back from China after a very short trip. They are compiling an update that we will see shortly. We wish everyone Merry Christmas and Happy Holidays.

                  UPDATE: MONDAY, DECEMBER 15, 2008

                  There will be no update this week as senior management is in China. Please check back next week.