I want to congratulate you on your first batch of fumed
silica from the pilot plant. I expect you are all super satisfied to have
reached this milestone, I know I am as well as I’m sure many other investors. I
do have a question though as it was not clear in the NR, it states the FSR
operated for one week, can you confirm what was the quantity of fumed silica produced
during that week of runtime?
The transition to semi-continuous production will significantly scale up material throughput, increasing feedstock input from 20–30 kg per batch to over 480 kg per day across two operational days. This phase targets the production of at least 200 kg of commercial-grade fumed silica, enabling expanded validation efforts, supply chain engagement, and pre-commercial market trials. The data and insights gathered from this stage will be pivotal in de-risking full-scale industrial deployment and advancing the technology toward commercialization.
I,ll take a stab at this ,with guesswork and assumptions A 480 kg load is expected to yield 200 kg of FS,so about 40%. Increasing load from 20-30 kg so I assume that's the size that is being used in those early tests,with a straight line conversion of 40%, that would produce 8 to 10 kg of FS.
also I don't see in the NR that the plant was in operation for a week,it says each test cycle takes 2 weeks,i assume that is a complete test from cold start to cooled down,product testing and reactor inspection.