Hi Peter,

For the higher heat industries that are being targeted for high-powered torches, will Pyrogenesis be designing and building larger plasma torch systems that can be installed for trials and data collection for any of multiple industries and applications, or are these torch systems specially built and customized for each particular application and end-user's facility? And do you expect the completion of future trials in these heavy industries to be more streamlined as compared to those done for iron pelletization induration? How will the experience gained from running the iron pelletization & other previous torch trials benefit future projects?  


At what stage do trials & pilot projects with plasma torches evolve into an established process that no longer requires this testing, and can be considered a plug-and-play replacement of burners with torches? Is there a specific data collection requirement and/or process modeling validation that is needed from the first industrial application users in these torch trials, beyond which enough is gathered to jump straight into replacement? Or will it just naturally happen as the technology becomes more widely accepted?


Regarding the two stages of the Furnace Electrification collaboration with GE Vernova, would you be able to provide an estimated time frame for the completion of these stages? In the press release, it was also mentioned that a "Furnace Electrification agreement" with GE Vernova is “next”'; my understanding is that it is pending the successful completion of both stages, is that the case? 


Thank you!

Sign in to ask the company to answer this.

Join the conversation about PyroGenesis Inc.

Reply

Replies

  1. Dear Majict,

     

    Thanks for posting again.


    this is a long one.  Bear with me, and let me try and answer your questions as follows:

     

    Q:

    For the higher heat industries that are being targeted for high-powered torches, will Pyrogenesis be designing and building larger plasma torch systems that can be installed for trials and data collection for any of multiple industries and applications, or are these torch systems specially built and customized for each particular application and end-user's facility? And do you expect the completion of future trials in these heavy industries to be more streamlined as compared to those done for iron pelletization induration? How will the experience gained from running the iron pelletization & other previous torch trials benefit future projects?  

    A:

    In general, a plasma torch system can be installed in a variety of industries or applications where the same level of power is required. However, certain applications require some customization, as it’s not only a matter of providing heat but also of providing a certain atmosphere for a process or product. That is not different from the case of burners, where different fuels can be burned depending on the process (e.g. certain chemistry or temperatures required). The ability to adapt to cater to those applications is a competitive advantage of PyroGenesis, where we not only are strong in designing and building the plasma systems but also in process design and optimization (to be able to implement plasma).

     

     

    Q:

    At what stage do trials & pilot projects with plasma torches evolve into an established process that no longer requires this testing, and can be considered a plug-and-play replacement of burners with torches? Is there a specific data collection requirement and/or process modeling validation that is needed from the first industrial application users in these torch trials, beyond which enough is gathered to jump straight into replacement? Or will it just naturally happen as the technology becomes more widely accepted?

    A:

     In general, we anticipate that plasma torches will evolve into an established product as users buy multiple plasma systems, and operate them long enough, so they learn and own the technology (as they did once with burners), and they feel more comfortable managing the risk of a big technology shift.

     

     

    Q:

    Regarding the two stages of the Furnace Electrification collaboration with GE Vernova, would you be able to provide an estimated time frame for the completion of these stages? In the press release, it was also mentioned that a "Furnace Electrification agreement" with GE Vernova is “next”'; my understanding is that it is pending the successful completion of both stages, is that the case? 

    A:

    The timeline cannot be disclosed at this time as it involves other partners that will participate in the different projects and their involvement is not public yet.

     

    Hope that Helps

    PPP