Just to refresh...



Based on :

- estimated frack-time 2 weeks
- testperiod 4 weeks
- using the same frack-equipement
- Talisman that has said all 3 wells will be completed late Q2/early Q3

week 18 spudding of Fortierville Hz
week 18 end of thaw period
week 20 start fracking of Gentilly
week 22 start testing of Gentilly
week 23 Fortierville TD
week 23 start fracking of LeClercville(not a Qec well)
week 25 start testing of LeClercville
week 26 results from Gentilly
week 26 start fracking of Fortierville
week 28 start testing of Fortierville
week 29 results from LeClercville
week 32 results from Fortierville


RGDS

Join the conversation about Questerre Energy Corporation.

Reply

Replies

  1. Thanks Domus for that.

    It's good to be able to see the "results" light at the end of the tunnel of these dog days drifting lower every day. It's way oversold considering the great results from St Edouard site. So much so I jumped in today and bought as many more that I had funds available for. We all know where it is eventually headed so anything in this range is a bargain even if it does up my average cost. The market will eventually have to acknowledge the huge value qec is sitting on. And now we are only months away from tying in to the grid and starting production.

    Cheers

    Inceptus