If you tuned in to watch the Diamond Creek webcam today (Monday 14Dec09) you saw the almost cured foundation exposed, the forms having been taken down from their sides. Construction workers are busy moving dirt back up against the outside of that foundation, and utility trenches are being dug to access the mill along that perimeter also.
The pit for the crusher is being created just to the west of the mill site.
On Wednesday they plan to erect the steel structures (with cranes) around the mill site perimeter. That way an enclosure will make it warmer to pour the concrete floor, and the curing will be faster as well.
I was surprised to see that there are no new tailings presently piled at Diamond Creek; I’m told that that is because they hauled the fresh tailings only to an intermediate stop coming down from the mountain (“the corral”) because of the pressure of the time constraints last month. In any case, those tailings will be accessible for input at Diamond Creek when it’s finally ready to produce.
IdahoSilver, I don’t know yet about the hiring decisions for the mill ops.