Permit

Glad to be on the good board! Does anyone know if they have already applied for the Cyanide permit? From what I understand it is a lengthy process ...at least 6 months.

TIA,

Macod

Join the conversation about Silver Falcon Mining.

Reply

Replies

  1. Welcome to a great board.

    The PR stated that the cyanide permit has been submitted. We are working with a 3rd party smelting client, they can be put under contract with the temporary location. Waiting on another PR regarding status of Metallurgical building, which contains smelter, vault and assay lab.

    1. The PR stated that "Permiitting is underway". If I had to guess I don't think they have submitted the permit yet. RK did tell me permit is a lot farther along, but frankly I don't believe him.

      I know the main concern is drilling, but it would be a huge benefit to get the mill working efficiently IMO. Who knows maybe they will surprise me with news to the contrary at the broker meetings.

      1. FWIW: a closed circuit leeching system has been in the plan since (at least) the shareholders meeting held in september 2011. Christian Q admitted to me at that time that they were having difficulty separating the precious metals out of the concentrate being produced by the mill. At that point in time it was already publicly known that the dore was being smelted from a mysterious "super concentrate" which he explained as being concentrate that had to be run though the system at least 4 times. From their press release on 03/01/12 we now know that it was not a "cost effective alternative"

        Best regards to all...

        Have a nice day!

        1. Ok I hope I am wrong on that. On the Idaho DEQ website it lists who has Cynaide permits in Idaho and mentions one that is proposed (no mention of Diamond Creek). I did contact them and they wrote:

          "I am responding to your question about how long it takes to get a cyanidation
          permit. Once an application is received the process takes 180 days for the DEQ
          Director to approve or disapprove an application. Of course it also takes time
          to prepare a high quality application."

          http://www.deq.idaho.gov/permitting/waste-management-permitting/cyanidation.aspx

          1. Just thinking out loud... Why do we keep the mill running if we can't separate the gold and silver without using a cyanide circuit? Apparently we are not breaking even and can't do any better until we get the permit and start using cyanide. This may make a few mad but what else is there. lleno

  2. Hey, Macod, welcome to the board. It's nice to see some of the good posters migrating over here where we can have a civil discourse.

    As to your question about the permit, I haven't heard anything. And you're sure not going to hear anything from SFMI. It has been two years since the mill started running, and I sure hope it wasn't just recently that they realized that they were running at such low recoveries and needed the extra circuit. Presumably they applied for the permit a while ago.

  3. I talked to the company about the permit and there was no time line given. However when they first considered using this option, they first contacted the regulators and they gave them the verbal OK that the system they planned to install would be able to be approved, so they apllied on that basis.