Cyanide Permit : Question/Answer from Idaho DEQ State Office

can you tell me if SFMI (Silver Falcon Mining,Inc.) has applied for a cyanide permit on their DIAMOND CREEK MILL FACILITY, MURPHY, IDAHO, USA. ANSWER

They have entered discussions with DEQ regarding the permitting process. I cannot give you any more detail as I have left the position of Cyanidation Permit Program management.

Staff Contact

Mine Project Coordinator
Bruce Schuld
DEQ State Office
Waste Management & Remediation Division
1410 N. Hilton
Boise, ID 83706
(208) 373-0554
[email protected]

Apparently someone else at DEQ is the Mine Project Coordinator??

Join the conversation about Silver Falcon Mining.

Reply

Replies

  1. I presume that even with a so-called "closed circuit", SFMI will still need a permit for the cyanide circuit. There still is the matter of storing and handling industrial quantities of cyanide.

    Amazing, though, that after 2 years of miserable recovery they still have not yet even applied for the permit. Who in the hell has been watching over the mill? (I know the answer.) In any other company, anyone letting a fiasco like this go on for two years without realizing there was a problem, identifying it, and correcting it, would be summarily canned.

    And BTW, if indeed no permit application has been filed yet, then PQ's quote in the latest PR that "Permitting of a proper, legal, safe and environmentally friendly circuit is underway" is just more dishonest weasel wording. What does "underway" mean? That they've started thinking about it? Can't tell you how sick I am of this kind of crap.

    There are a few events that would really help the share price. Significant revenue and outstanding drill results are the biggies. The low recovery rate means that the event that shold have already occurred (significant revenue) has now been moved down the road, probably at least another year (6 months for the permit alone). As of now, we are now pinning all our hopes on the drill results, which of course also depend on getting the permit to drill. I sure hope the word on the street that they have actually applied for the permit and are just waiting for approval to drill is true.

    While there are other events that will help the share price, they are secondary goals that are insignificant in comparison to the primary goals of revenue and drill results. Changes to the BOD? Mostly cosmetic change that should have occurred long ago. Getting a new boss with mining experience? Again, something that should have happened long ago (pre-RS), and primarily a means to have someone who knows what they are doing get the drill results we need- which is a primary goal. And how much did having RS around help the sp? Getting financing? Again, a secondary goal to help speed achievement of the primary goals.

    In summary- Get the blasting permit and drill.

    1. I am wondering if the blasting permit has been submitted now....do we know it is factual?

      Since we have come to realize sincerity isn't SFMI's strong suit. What is real and what isn't?

      1. From what I have read and heard, the blasting permit was submitted and SFMI is waiting for approval. But maybe what they actually said was that the permitting process was "underway". My impression is that they probably have submitted the blasting permit, but with this latest stuff with the cyanide permit it's impossible to tell. There is a serious credibility problem here. Not only is nothing being done to address it, but the weasel wording continues.

        1. This was RK reply to the cyanide permit as stated in the PR

          Permitting of a proper, legal, safe and environmentally friendly circuit is underway and all necessary engineering will be done by recognized suppliers of the equipment to insure a proper and lawful compliance to the Diamond Creek Mill operations

          1. That is a quote from PQ, supposedly. The question is, what does "underway" mean? If the reports from the permitting office are correct, "underway" doesn't include submitting the permit.

  2. Question:

    Thanks Rob. Can you tell me if Silver Falcon Mining, Inc. has applied for a
    cyanide permit on their Diamond Creek Mill Facility?

    Answer:

    John:

    They have not submitted an application at this time.

    Rob

    Rob Hanson
    Mine Waste Program Manager
    Idaho Department of Environmental Quality
    1410 North Hilton
    Boise, Idaho 83706
    phone: 208-373-0290
    cell: 208-761-4480
    fax: 208-373-0154
    [email protected]

    Response to my original question of how long it will take to get a permit approved:

    John:

    I am responding to your question about how long it takes to get a cyanidation
    permit. Once an application is received the process takes 180 days for the DEQ
    Director to approve or disapprove an application. Of course it also takes time
    to prepare a high quality application.

    If you would like to discuss further, feel free to give me a call.

    Rob

    Rob Hanson
    Mine Waste Program Manager
    Idaho Department of Environmental Quality
    1410 North Hilton
    Boise, Idaho 83706
    phone: 208-373-0290
    cell: 208-761-4480
    fax: 208-373-0154
    [email protected]

    1. I am assuming it all depends on the upcoming broker's meeting on the 26th. Money is an issue..

      SFMI needs money to file 43 101.....drilling program....hiring

      PQ and RK are entering the Shark Tank...due or die on the 26 and 27th of March. JMHO!!

  3. Garick's comment about this meeting in LI being a do or die hopefully was a joke, because there was no truth to that statement. The meeting in NY is to expose SF to brokers AND to hopefully convince them to spread the word on how undervalued and the potential our gem has.

    Money is in place to start the drills. Waiting on permits.

    I will say this, Denise is probably gone right before this meeting, BUT CQ needs to go back and play his Banjo back home as well, and just wait till Daddy gets rich on the sale of his 2 companies because he's NOT helping. I believe we get 2 BOD changes short-term.

    1. Bouts- Does "waiting on permits" mean that they have been submitted? It's what I've heard, but maybe it's just a misinterpretation of what RK said that was simply more weasel wording intended to make people think that the permits have been submitted.

      1. I heard all paperwork has been submitted for the permits needed to blast and drill. Contractors have been picked and ready.

    2. I am bi-polar.....I didn't take my meds today.

      As far as the brokers meeting in a couple of weeks. RK and PQ won't be able to spin bullshit on projected completion dates or false numbers as they have done with the shareholders.

      It is of my opinion....telling them they will file the 43 101 in the future or SFMI has already filed the 43 101 will have a huge impact on the brokers decision to expose SFMI to the investment world.

      Also....if DQ is still on the board along with her son, I don't see the brokers looking kindly on that scenario.

      Permit has been issued for the drilling, hopefully we get it approved prior to the brokers meeting. The cyanide permit hasn't been filed...according to the PR.

      Brokers will ask PQ and RK, is the capital in place and if so where did the capital resources come from? We have been placed in the dark as shareholders until the reports come out showing further dilution or a deal cut with a lender.

      Brokers will ask....how much more dilution do you anticipate will occur?

      Am I paranoid....NO Do I question SFMI because I have an investment in SFMI and their beholden to the shareholders...YES

      I was at the last shareholder meeting. Many expectations of projected dates have fallen short of being fullfilled. Which I can understand because of uncalculated chain of events.

      As for me..I am in it to win it.

    1. Slammin- Hadn't seen that. Nice find. It's basically a repeat of the PR, but with a couple diagrams and some extra stuff about cyanide included. The diagrams are fine, but they're going to need a lot more than that for a permit appplication, which seemingly has not yet been submitted. They don't let you play with cyanide on the basis of a diagram based on a manufacturer's web site.

      Couple things to note- It's "metallurgy", not mettalurgy. And they also should decide which spelling of "flotation" they are going to use- the standard form, or the variant "floatation". Stuff like this isn't impressive when you're submitting permits.

  4. pic- Paranoid? You mean after being told for a year that production at the Melba mill was imminent, that initial grades at the Diamond Creek mill were 0.75 oz, that the waste ore was 4 oz/t (personally, to my face at the SHM), NOT being told for two years that the mill was running at 20% recovery, and after being told by PQ that permitting for the cyanide circuit is "underway" that "underway" according to the permitting office doesn't include having submitted the permit, that wondering about the true state of the blasting permit is "paranoid"? I'd say it's learning from experience.