destroyed by fire in 1968. The mine re-opened in January 1982 designed to produce
684 kg gold from the upper levels only. Production reached 49.76 kg by July 1982.
Grades of ore only reached 4.8 g/tonne, so operations were terminated in May, 1983.
In 1983 Lathwell Resources Ltd. negotiated an option agreement with Brinco.
Exploration drilling during 1983 intersected the 97 stockwork with 9 holes. Average
thickness below 33 level was 3.45 m averaging 9.26 g/tonne (200000 tonnes of ore). In
1984 a D shaft ore reserve between the 26 and 36 levels was estimated as 1 203161
tonnes averaging 7.89g/tonne. Drill holes confirmed the presence of several new
stockworks (parallel 97 veins) on the 33 level. However Lathwell dropped the option
after phase I exploration work late in 1984.
1985 (November) to 1987: The San Antonio property was optioned by San Antonio
Resources, jointly owned by Inco Ltd., Quest Resources and private investors. A 6640
m underground drilling program was carried out that defined a "mineral resource" of
420 000 oz or 13 063 kg gold. In 1987 Kilborn-Cassiar confirms mineable reserves of
1,469,690 tons grading 0.2080zlton with operating costs of US $322/oz
1989: Early in the year Cassiar (Kilborn) estimates 1.23 million tons at an average
grade of 0.223 ozlton mineable reserves. Cost US $230/oz for the first 3 years, capital
cost $11.2 million for extending the A shaft 900ft to the 16th level and deepening the D
shaft to access the ore below the 26th level. Later in 1989 Rea Gold acquires San
Antonio from Cassiar Mining. Estimated mineable ore below the 26th level was 1.2
million tons grading 0.22 ozlton and 301,400 tons grading 0.192 oz above the 26th
level. Capital cost was estimated at $18.8 million, operating cost at $78.53/ton.
1993-present: In 1993 Rea Gold begins a pre-feasibility study involving underground
drilling in 1994. In 1994 Rea Gold begins engineering study to complete feasibility
study. Projected production 60 000-70 000 ozlyear, cost US$250/oz. Capital cost to
mine 1000 tons/day is $30 million. Mineable reserves >400000 oz.
In 1995 after an underground exploration drilling program in 1994 estimated 1.95
million tons grading 0.197 o.p.t., subsequent recalculations arrive at nearly 3 million
tons grading 0.275 o.p.t. Capital cost for bringing the mine back into production is
estimated at $30.3 million. Operating costs $61.22 per ton or $US 242 per ounce of
gold. Milling 1000t.p.d. upgraded within 2 years. During this period operating revenue
of $5.6 million from processing of development ore.
Gold production at San Antonio:
1932-68 41,519 kg (1,334,892 oz.)
1982 estimate 344 kg 11,050 oz.
1983 estimate 137 kg 4,393 oz.
Siver production:
1932-68 5,978.2 kg