  1. YES, YES and YES....

    What I have been told by Brian Briggs is now Bankable FS and financing and permits keep pushing forward.

      1. Feasibility Study becomes bankable after debt financing due diligence review is completed.

        They have been developing a list of debt financiers who will be involved in the debt portion of project financing. Once a lead bank is chosen and the FS is complete a review team of engineers, geologists, and environmental specialists will be chosen by the bank (separate from our own team). They will complete a full review of the project FS, paid for by us, and will come up with questions, comments or concerns on what we have developed. Our FS team of consultants as well as in-house staff will answer their questions and comments and the end result is that the banks will certify the FS meets the standards for a Bankable Feasibility Study.

        This process takes approximately 6 months once the final FS is completed by our team. The FS will than become a BFS

      2. Bankable Feasibility Studies by Resources Gold Technology

        Resources Gold Technologies offers bankable feasibility studies to owner / operators who have completed pre-feasibility studies and metallurgical study and are ready to proceed with final project evaluation. Preliminary work can also be included as part of a bankable feasibility study.

        Bankable feasibility studies are the highest level of project evaluation in the form of a study. These investigations and reports form the basis for implementation of a gold mining project and the construction of a gold processing plant. In many cases, these studies are used by owners as the basis for raising capital finance to construct a gold processing plant. All technical and financial aspects of a potential project are investigated during a bankable feasibility study.

        Due to the extensive nature of a bankable feasibility study these investigations typically take several months to complete. During this bankable study, the process flow sheet is refined and mathematically the mass, water and gold balances are modeled. Water and energy requirements are determined as well as anticipated consumption of reagents. Once this is complete, the bankable feasibility study progresses to produce a detailed costing combined with a financial analysis, operational and capital expenditure.

        Bankable feasibility studies produce expected construction programs and investigate transport and site logistics in detail. Cash flow requirements are analyzed together with projected project repayment periods and revenue generation in various financial models. Key suppliers are identified as well as manpower requirements for construction and operation of the gold processing plant. In certain cases where large capital outlay is involved, owners may choose to construct and operate a pilot plant to confirm the outcome of the bankable feasibility study.

        http://www.resourcesgoldtechnology.com/bankable-feasibility-studies.html