Looking at the cross section I think bl10-2 should be revisited and drilled to depth... untill it runs out of structure. The grade increases at depth. If it continues to increase at depth the resource will grow exponentially.

BORDEN LAKE -- SELECTED DRILL HOLE ASSAY INTERVALS

DDH From (m) To (m) Width (m) Au (g/t)

BL10-02 4 23 19.0 0.4
BL10-02 37 128 91.0 2.0
iIncluding
BL10-02 73 84 11.0 3.5
also including
BL10-02 91 112 21.0 3.2
including
BL10-02 106 111 5.0 5.3

Join the conversation about Probe Mines.

Reply

Replies

  1. While they are there they should continue 10 - 3 for the same reason.... looks like 10 3 could go a very long ways before it runs out of structure.

    JMHO

    1. I wasn't expecting rich cores from borden-it being known as a large low grade deposit for now- it will take alot of drilling to prove up . However LSG drill core should be on the way soon and it's drill results made for a big jump for it's stock price - hopefully they will do the same for us.