Drilling and Assay Time Reference...

FWIW... About this time in 2007...

re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.

Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).

re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.

Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.

Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.

red911

P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".

Join the conversation about Sage Gold Inc.

Reply

Replies

  1. SGX is now into its 14th day of drilling Golden Extension vein structures.

    Based on historical drilling average of 54 metres per day, which includes comparable number of drill location changes...

    SGX has likely drilled at least 700m, or 7 of its planned 15 or so 100m holes... maybe a little more or less.

    That's about half way through the 1st 1,500m phase of drilling. Another 2 weeks and drilling will be complete IMO.

    Rgarding assays... the relevant question here is whether SGX has sent individual cores for assay as they have come out of the ground OR if they are holding on to cores to send as a group... If they have sent the first 3 or so holes drilled in the first week of drilling it is POSSIBLE they have recevied these assays or will be receiving them over next few days.

    What do people think... cores sent individually or as a group?... Obvious answer is that it depends what the geologists see in them... therefore, based on surface work (VG and high-grade sampling results) can we be somewhat confident these cores will be sent for immediate assay?

    red911

    Drilling and Assay Time Reference...

    posted on Jun 10, 09 08:03AM

    FWIW... About this time in 2007...

    re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.

    Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).

    re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.

    Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.

    Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.

    red911

    P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".

    1. Hey Red911

      The Company Replied with this when asked about timelines and releasing News as it comes in.

      Dear shareholder,

      SAGE Gold will release news and updates on Jacobus and Paint Lake accordingly in a timely manner as stated previously.

      Regards,

      AGORACOM Investor Relations

    2. Will keep posting until we get results...

      Now 21 days into drill program at Golden Extension. At historical rate of about 54m per day, they should be at just over 1,100m drilled. First phase orignially announced to be 1,500m so they could be complete by about this time next week. This rate of 54m per day based on a couple of historical programs at Jacobus (see below) and does include time for a few drill location changes. Also, SGX has delivered results in this time as well... 'IF' first few cores were submitted after the first week or so, they could be ready very soon. Big question is 'IF'. 'IF' not we wait until who knows when.

      Questions I have about results... do veins get thicker (at least a little) at depth? have they discovered any new veins? have they been successful intersecting multiple veins? will high-grade shallow DRILL results warrant a halt? will we see SGX positive results influence KXL share price (for a change)? are they continuting to strip and trench to the NW? etc.

      red911

      ------------------------------------------------------

      14 Days into Golden Extension Drilling...

      posted on Jun 22, 09 10:49AM

      SGX is now into its 14th day of drilling Golden Extension vein structures.

      Based on historical drilling average of 54 metres per day, which includes comparable number of drill location changes...

      SGX has likely drilled at least 700m, or 7 of its planned 15 or so 100m holes... maybe a little more or less.

      That's about half way through the 1st 1,500m phase of drilling. Another 2 weeks and drilling will be complete IMO.

      Rgarding assays... the relevant question here is whether SGX has sent individual cores for assay as they have come out of the ground OR if they are holding on to cores to send as a group... If they have sent the first 3 or so holes drilled in the first week of drilling it is POSSIBLE they have recevied these assays or will be receiving them over next few days.

      What do people think... cores sent individually or as a group?... Obvious answer is that it depends what the geologists see in them... therefore, based on surface work (VG and high-grade sampling results) can we be somewhat confident these cores will be sent for immediate assay?

      red911

      Drilling and Assay Time Reference...

      posted on Jun 10, 09 08:03AM

      FWIW... About this time in 2007...

      re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.

      Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).

      re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.

      Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.

      Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.

      red911

      P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".

      1. Hey Red911

        This was Relayed on June 8th as well, just a guess but I think they had a few hundred meters drilled by the 8th of June. The time line might be 28 days already lets hope.

        "Thank you for you inquiry, the following response was provided by management.

        The first vein drilled was Vein 1, the original Golden Extension. The Magnetic maps are shown on the PPT presentation on the SAGE website, Slides 14-15."

      2. I can't help but think that we might be a few few drill phases away from really seeing what's there in the GE.

        10 to 15 holes at 100 - 150 m will interect veins at a shallow depth, not anywhere near where Red suggested that veins 1 and 4 might intersect (@ 200 m). A 100m hole drilled at a 45 degree angle will go to a depth of 70m (150m hole will go to 105m)... so we will see nothing more than a small vein intersection and possibly 2 if the veins are close.

        I suppose the only telling evidence that us armchair geos (using the term loosely) might see is a slightly wider intersection of vein which would be nice to see. Other than that we will only confirm that the vein goes down.

        I think the most useful info that this drill program might do is help to determine the geometry of the veins that will help ensure future drill holes are not blanks and will continue to hit the veins at depth.

        1. well being a holiday this week i don,t expect any news , but we should have news the wek after if not there maybe a problem, there are no lab back ups

      3. 28 days x 54m per day = 1,512m

        Are they done the first phase? News this week? Or, do we wait until after CPW-v vote and approval process late-July?

        If previous drill programs at Jacobus are any indication, then yes but anything can happen. Also remember, they have had assays back for some holes in this amount of time for similar programs in the past.

        red911


        21 Days into Golden Extension Drilling...

        posted on Jun 29, 09 02:39PM

        Will keep posting until we get results...

        Now 21 days into drill program at Golden Extension. At historical rate of about 54m per day, they should be at just over 1,100m drilled. First phase orignially announced to be 1,500m so they could be complete by about this time next week. This rate of 54m per day based on a couple of historical programs at Jacobus (see below) and does include time for a few drill location changes. Also, SGX has delivered results in this time as well... 'IF' first few cores were submitted after the first week or so, they could be ready very soon. Big question is 'IF'. 'IF' not we wait until who knows when.

        Questions I have about results... do veins get thicker (at least a little) at depth? have they discovered any new veins? have they been successful intersecting multiple veins? will high-grade shallow DRILL results warrant a halt? will we see SGX positive results influence KXL share price (for a change)? are they continuting to strip and trench to the NW? etc.

        red911

        ------------------------------------------------------

        14 Days into Golden Extension Drilling...

        posted on Jun 22, 09 10:49AM

        SGX is now into its 14th day of drilling Golden Extension vein structures.

        Based on historical drilling average of 54 metres per day, which includes comparable number of drill location changes...

        SGX has likely drilled at least 700m, or 7 of its planned 15 or so 100m holes... maybe a little more or less.

        That's about half way through the 1st 1,500m phase of drilling. Another 2 weeks and drilling will be complete IMO.

        Rgarding assays... the relevant question here is whether SGX has sent individual cores for assay as they have come out of the ground OR if they are holding on to cores to send as a group... If they have sent the first 3 or so holes drilled in the first week of drilling it is POSSIBLE they have recevied these assays or will be receiving them over next few days.

        What do people think... cores sent individually or as a group?... Obvious answer is that it depends what the geologists see in them... therefore, based on surface work (VG and high-grade sampling results) can we be somewhat confident these cores will be sent for immediate assay?

        red911

        Drilling and Assay Time Reference...

        posted on Jun 10, 09 08:03AM

        FWIW... About this time in 2007...

        re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.

        Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).

        re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.

        Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.

        Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.

        red911

        P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".

        1. Red,

          What do you think will happen to the share price if the drill results are very similar to what Kodiak drilled on the Golden Mile? Their share price is way off because the veins have yet to show economic viability.

            1. Replying to @JayL

              im asking about share price. Are we going to languish if we get same results or is that a positive and the share price will reflect it.

          1. "What do you think will happen to the share price if the drill results are very similar to what Kodiak drilled on the Golden Mile? Their share price is way off because the veins have yet to show economic viability."

            No idea.

            Personally, I hope drill results show somewhat of a different structure on SGX Jacobus East than initial KXL results. By this I am referring to the fact that initial KXL drilling into Golden Mile primarily concerned a single narrow NWerly vein. SGX system seems to have multiple criss-crossing veins where it is pssible to interesct 2 or maybe 3 with a single very shallow 100m drill hole. Higher concentration of veins with similar gold concentrations per vein would seem to mean more gold and close to surface.

            Also, I don't remember hearing language like this in any of KXL NRs to date: "It is apparent that the stripped area now encompasses the contact zone between the Elmhirst intrusion and the surrounding volcanics." or "Vein 9 comprises two discrete veins separated by up to 15 metres of sheared carbonatized and mineralized wall rock. Visible gold is present within the sheared wall rock between the north and south offshoots." Remember this 15m zone was not sampled.

            Key results for me will be Vein 4 and Vein 9. What effect on share price will be... obviously no idea. Who does? As long as they uncover what they expected (i.e. high-grade gold) and plan to drill more I will be happy.

            P.S. EXS-v moving today. They are expecting results from 2 projects... 1 being Eastford Lake project just south of Kerrs property.

            red911

        2. Now actually (at least) into 36th day of Golden Extension drillind based on drilling announcement on June 8th.

          35 days x 54m per day = ~1,900m

          Would be hard to believe they are not finished or almost completely drilling 1,500m by now. Also highly likely assays (at least some) have been completed and received.

          Why no news? Your guess is as good as mine... Still analyzing assays? Many assays sent back for re-assay? Found nothing worth reporting? Everyone on holidays? Convenient 'delays' to correspond with CPW-v approval?

          One thing if for sure... SGX has been abnormally quiet and tight-lipped during the past 3-4 months IMO. One look at drilling announcement is proof of this. Why? Again, your guess is as good as mine. I do know even I am getting tired of all the 'waiting' LOL.

          red911

          28 Days into Golden Extension Drilling...

          posted on Jul 06, 09 08:16AM

          28 days x 54m per day = 1,512m

          Are they done the first phase? News this week? Or, do we wait until after CPW-v vote and approval process late-July?

          If previous drill programs at Jacobus are any indication, then yes but anything can happen. Also remember, they have had assays back for some holes in this amount of time for similar programs in the past.

          red911


          21 Days into Golden Extension Drilling...

          posted on Jun 29, 09 02:39PM

          Will keep posting until we get results...

          Now 21 days into drill program at Golden Extension. At historical rate of about 54m per day, they should be at just over 1,100m drilled. First phase orignially announced to be 1,500m so they could be complete by about this time next week. This rate of 54m per day based on a couple of historical programs at Jacobus (see below) and does include time for a few drill location changes. Also, SGX has delivered results in this time as well... 'IF' first few cores were submitted after the first week or so, they could be ready very soon. Big question is 'IF'. 'IF' not we wait until who knows when.

          Questions I have about results... do veins get thicker (at least a little) at depth? have they discovered any new veins? have they been successful intersecting multiple veins? will high-grade shallow DRILL results warrant a halt? will we see SGX positive results influence KXL share price (for a change)? are they continuting to strip and trench to the NW? etc.

          red911

          ------------------------------------------------------

          14 Days into Golden Extension Drilling...

          posted on Jun 22, 09 10:49AM

          SGX is now into its 14th day of drilling Golden Extension vein structures.

          Based on historical drilling average of 54 metres per day, which includes comparable number of drill location changes...

          SGX has likely drilled at least 700m, or 7 of its planned 15 or so 100m holes... maybe a little more or less.

          That's about half way through the 1st 1,500m phase of drilling. Another 2 weeks and drilling will be complete IMO.

          Rgarding assays... the relevant question here is whether SGX has sent individual cores for assay as they have come out of the ground OR if they are holding on to cores to send as a group... If they have sent the first 3 or so holes drilled in the first week of drilling it is POSSIBLE they have recevied these assays or will be receiving them over next few days.

          What do people think... cores sent individually or as a group?... Obvious answer is that it depends what the geologists see in them... therefore, based on surface work (VG and high-grade sampling results) can we be somewhat confident these cores will be sent for immediate assay?

          red911

          Drilling and Assay Time Reference...

          posted on Jun 10, 09 08:03AM

          FWIW... About this time in 2007...

          re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.

          Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).

          re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.

          Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.

          Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.

          red911

          P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".

          1. 42 days x 54m per day = ~2,200m

            Would have to think results are close... at least closer than last week LOL.

            Maybe they've started the second 1,500m by now?... Who knows.

            red911

            -------------------------------------------------

            35 Days into Golden Extension Drilling...

            posted on Jul 14, 09 10:41AM

            Now actually (at least) into 36th day of Golden Extension drillind based on drilling announcement on June 8th.

            35 days x 54m per day = ~1,900m

            Would be hard to believe they are not finished or almost completely drilling 1,500m by now. Also highly likely assays (at least some) have been completed and received.

            Why no news? Your guess is as good as mine... Still analyzing assays? Many assays sent back for re-assay? Found nothing worth reporting? Everyone on holidays? Convenient 'delays' to correspond with CPW-v approval?

            One thing if for sure... SGX has been abnormally quiet and tight-lipped during the past 3-4 months IMO. One look at drilling announcement is proof of this. Why? Again, your guess is as good as mine. I do know even I am getting tired of all the 'waiting' LOL.

            red911

            28 Days into Golden Extension Drilling...

            posted on Jul 06, 09 08:16AM

            28 days x 54m per day = 1,512m

            Are they done the first phase? News this week? Or, do we wait until after CPW-v vote and approval process late-July?

            If previous drill programs at Jacobus are any indication, then yes but anything can happen. Also remember, they have had assays back for some holes in this amount of time for similar programs in the past.

            red911


            21 Days into Golden Extension Drilling...

            posted on Jun 29, 09 02:39PM

            Will keep posting until we get results...

            Now 21 days into drill program at Golden Extension. At historical rate of about 54m per day, they should be at just over 1,100m drilled. First phase orignially announced to be 1,500m so they could be complete by about this time next week. This rate of 54m per day based on a couple of historical programs at Jacobus (see below) and does include time for a few drill location changes. Also, SGX has delivered results in this time as well... 'IF' first few cores were submitted after the first week or so, they could be ready very soon. Big question is 'IF'. 'IF' not we wait until who knows when.

            Questions I have about results... do veins get thicker (at least a little) at depth? have they discovered any new veins? have they been successful intersecting multiple veins? will high-grade shallow DRILL results warrant a halt? will we see SGX positive results influence KXL share price (for a change)? are they continuting to strip and trench to the NW? etc.

            red911

            ------------------------------------------------------

            14 Days into Golden Extension Drilling...

            posted on Jun 22, 09 10:49AM

            SGX is now into its 14th day of drilling Golden Extension vein structures.

            Based on historical drilling average of 54 metres per day, which includes comparable number of drill location changes...

            SGX has likely drilled at least 700m, or 7 of its planned 15 or so 100m holes... maybe a little more or less.

            That's about half way through the 1st 1,500m phase of drilling. Another 2 weeks and drilling will be complete IMO.

            Rgarding assays... the relevant question here is whether SGX has sent individual cores for assay as they have come out of the ground OR if they are holding on to cores to send as a group... If they have sent the first 3 or so holes drilled in the first week of drilling it is POSSIBLE they have recevied these assays or will be receiving them over next few days.

            What do people think... cores sent individually or as a group?... Obvious answer is that it depends what the geologists see in them... therefore, based on surface work (VG and high-grade sampling results) can we be somewhat confident these cores will be sent for immediate assay?

            red911

            Drilling and Assay Time Reference...

            posted on Jun 10, 09 08:03AM

            FWIW... About this time in 2007...

            re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.

            Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).

            re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.

            Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.

            Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.

            red911

            P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".

            1. Replying to @red911

              That's a good question red, I would have thought that the results of the first 1500 would be announced prior to starting the second but I could be wrong.

              1. Replying to @jordie

                I think most of us would have expected something by now as well, but its pretty tough to know whats going on these days with the upcoming Puma vote and especially how tight lipped mgmt has been as of late.

            2. Replying to @red911

              Tomorrow SGX be 49 days into GE drilling since official drilling announcement June 8th...

              49 x 54m per day = ~2,650m

              Remember this 54m/day is based on previous Jacobus Ni-Cu drilling (1 drill) and includes release of some assays.

              Would have to think there is no question initial 1,500m is complete. Based on previous non-response re: '2 phase drill program' woud seem likely they have altered plans and continued to drill more than initialy announced 1,500m IMO. This is nothing to complain about LOL. Maybe even added second drill? Maybe maybe not.

              We are starting to get well into 2009 summer exploration season... they have said they plan to strip and trench toward KXL border to establish unquestionable continuity with Golden Mile. Has this started yet? Have they uncovered additional metres of existing structure? Have they found any new structures via stripping and trenching and/or drilling? Have cores been sent for re-assay? Is there visible gold? Do results to date indicate potential for high-grade Au open-pittable resource? Who will be appointed to SGX board from CPW board/management? So many questions.

              CPW-v acquisition now approved by its shareholders. IMO we could get news at any time.

              red911

              42 Days into Golden Extension Drilling...

              posted on Jul 20, 09 09:04AM

              42 days x 54m per day = ~2,200m

              Would have to think results are close... at least closer than last week LOL.

              Maybe they've started the second 1,500m by now?... Who knows.

              red911

              -------------------------------------------------

              35 Days into Golden Extension Drilling...

              posted on Jul 14, 09 10:41AM

              Now actually (at least) into 36th day of Golden Extension drillind based on drilling announcement on June 8th.

              35 days x 54m per day = ~1,900m

              Would be hard to believe they are not finished or almost completely drilling 1,500m by now. Also highly likely assays (at least some) have been completed and received.

              Why no news? Your guess is as good as mine... Still analyzing assays? Many assays sent back for re-assay? Found nothing worth reporting? Everyone on holidays? Convenient 'delays' to correspond with CPW-v approval?

              One thing if for sure... SGX has been abnormally quiet and tight-lipped during the past 3-4 months IMO. One look at drilling announcement is proof of this. Why? Again, your guess is as good as mine. I do know even I am getting tired of all the 'waiting' LOL.

              red911

              28 Days into Golden Extension Drilling...

              posted on Jul 06, 09 08:16AM

              28 days x 54m per day = 1,512m

              Are they done the first phase? News this week? Or, do we wait until after CPW-v vote and approval process late-July?

              If previous drill programs at Jacobus are any indication, then yes but anything can happen. Also remember, they have had assays back for some holes in this amount of time for similar programs in the past.

              red911


              21 Days into Golden Extension Drilling...

              posted on Jun 29, 09 02:39PM

              Will keep posting until we get results...

              Now 21 days into drill program at Golden Extension. At historical rate of about 54m per day, they should be at just over 1,100m drilled. First phase orignially announced to be 1,500m so they could be complete by about this time next week. This rate of 54m per day based on a couple of historical programs at Jacobus (see below) and does include time for a few drill location changes. Also, SGX has delivered results in this time as well... 'IF' first few cores were submitted after the first week or so, they could be ready very soon. Big question is 'IF'. 'IF' not we wait until who knows when.

              Questions I have about results... do veins get thicker (at least a little) at depth? have they discovered any new veins? have they been successful intersecting multiple veins? will high-grade shallow DRILL results warrant a halt? will we see SGX positive results influence KXL share price (for a change)? are they continuting to strip and trench to the NW? etc.

              red911

              ------------------------------------------------------

              14 Days into Golden Extension Drilling...

              posted on Jun 22, 09 10:49AM

              SGX is now into its 14th day of drilling Golden Extension vein structures.

              Based on historical drilling average of 54 metres per day, which includes comparable number of drill location changes...

              SGX has likely drilled at least 700m, or 7 of its planned 15 or so 100m holes... maybe a little more or less.

              That's about half way through the 1st 1,500m phase of drilling. Another 2 weeks and drilling will be complete IMO.

              Rgarding assays... the relevant question here is whether SGX has sent individual cores for assay as they have come out of the ground OR if they are holding on to cores to send as a group... If they have sent the first 3 or so holes drilled in the first week of drilling it is POSSIBLE they have recevied these assays or will be receiving them over next few days.

              What do people think... cores sent individually or as a group?... Obvious answer is that it depends what the geologists see in them... therefore, based on surface work (VG and high-grade sampling results) can we be somewhat confident these cores will be sent for immediate assay?

              red911

              Drilling and Assay Time Reference...

              posted on Jun 10, 09 08:03AM

              FWIW... About this time in 2007...

              re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.

              Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).

              re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.

              Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.

              Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.

              red911

              P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".

              red911

              Reply in Sage Gold Inc.

              Now actually (at least) into 36th day of Golden Extension drillind based on drilling announcement on June 8th. 35 days x 54m per day = ~1,900m Would be hard to believe they are not finished or almost completely drilling 1,500m by now. Also highly likely assays (at least some) ...

  2. Further to this... According to NI 43-101 Jacobus East technicel report released today, dated May 29, 2009...

    "20.0 RECOMMENDATIONS:

    The Jacobus East Property has produced results which warrant follow‐up sampling and mapping leading to the definition of high‐priority drill targets. The geological setting, mineralization styles and high grade gold abundances are characteristic of Archean‐aged lode gold systems. Early emphasis on establishing drill targets will allow the bulk of sampling and mapping to run concurrently with the drill program. The recommended program (already in progress) will take approximately one month to execute and cost approximately CDN$429,000 (Table 4)."

    The recommended program they refer to includes 1,000m... obviouly SGX has already announced they plan to drill 1,500m... so expect 1 month timeline suggested in report to be a little longer. But remember, this 1 month timeline also includes assays. Program (sampling and mapping I would guess) was "already underway" as of date of this report, May 29, 2009. Therefore, my estimate of completion date of July 5, 2009 below may not be that far off... based on this info... everything should may be complete by end of 2nd week of July.... third week latest IMO. Assuming everything runs relatively smoothly of course.

    red911



    Drilling and Assay Time Reference...

    posted on Jun 10, 09 12:03PM

    FWIW... About this time in 2007...

    re: Drilling... SGX announced a 2,000m program at Jacobus Cu-Ni. They completed 6 holes (and reported assays from 1 hole) of this initial 2,000m drill program in about 37 days (about 54m per day). SGX then extended drill program to 3,800m and completed an additional 7 holes in another about 33 days (also about 54m per day). Therefore, to change drill locations ~13 times and drill 3,800 meters took 70 days and averaged just over 54m per day.

    Therefore... SGX Golden Extension initial program started on or about June 8th... estimated to be 1,500m... using 54m per day (which was exact same rate in previous Jacobus drilling)... IMO this drill program could be complete in about 28 days (July 5th). They have indicated drilling 15 or so 100m holes. However, they have also said multiple holes (I am guessing 2 or max 3) could be drilled from same drill location. Therefore, they will likely not need to move drill 15 times... IMO 8-10 movements maximum will be necessary (i.e. less than 2007 program when they changed 13 times and still averaged 54m per day).

    re: Assays... It seems in 2007 that other than the 1 hole reported after the first 6 holes, all assays were submitted for assay simultaneously after the entire program was completed. Remaining assays were expected in early August. Would also seem the 1 hole reported was sent for immediate assay because it did contain "best nickel hole to date at Jacobus". Therefore, safe to assume that if other holes looked of similar quality they would have also been sent for immediate or near-immediate assay.

    Therefore, if previous Jacobus program is any indication... and I can't think of any reason why it wouldn't be... 1 drill, virtually same location, likely same crews... if the first few holes look promising enough to send from immediate assay, some assays would also be possible by this estimated drilling completion date of July 5th. With all the talk of visible gold on surface and found in the samples one would think this will be the case.

    Would multiple high-grade hits per hole near surface over multiple holes warrant a halt or two? Me think yes. Not dealing with channel samples anymore. Let's hope.

    red911

    P.S. I think this is a possible completion date but I still say SGX will delay these results until Puma transaction closes. I hope I am wrong but I have seen this before. Don't agree with it but it happens. All we can do is hope that it closes sooner than they anticipated and not "sometime in July".

    1. Anybody know what the allowable tonnage is on the bulk sampling permit? If Sage managed to process some ore with a nice grams/tonne ratio, that could generate some excitement for the SP as well as put some cash in the kitty.

      Any time a junior explorer can go from a cash-burning entity to a gold-producing one ( even within the limitations of a bulk sample permit) that is a very positive step. And judging by the good grades encountered in the channel and grab samples, we may be in for some long-overdue excitement.

      JMO

      1. quack:

        Glad you are still here.

        Do you know if SGX has applied for a bulk sampling permit? Agree this would be great news and differentiate SGX from average explorer. You think this is possible? High-grades on surface from multiple veins in very close proximity would seem to be conducive to very productive bulk sampling.

        Was glad to see NI 43-101 on Jacobus East. Shows they are serious about making this discovery legit every step of the way, from the get-go. Always good to have complete should prospective partners, investors, etc. request.

        red911

        1. What I know is...I don't know nearly enough about bulk sampling.

          I like the our chances of the criss-crossing, surface expression of gold-bearing veins being an excellent choice for a bulk sample, especially as it is to be conducted simultaneously with the drill program. It'd be nice if we had good grades at surface and continuing on, possibly improving at depth, which so far has been an elusive prize in the BGGC.

          As far as the permit goes, I don't know if they have it in hand yet. They may not even require one, if the bulk sampling falls within certain (low) parameters in the course of their exploration activities.

          However, if they have loftier plans than they are telling us about just yet, they will require an "Advanced Exploration" permit for those activities. And I think that propels them in a different tax bracket, so to speak. More money to be spent, more obligations to be met, more permits required, more environmental studies, and on and on. I believe, if I'm not mistaken, that's why they have to stay within a certain threshold of so many allotted square meters of stripping and trenching before triggering the "Advanced Explorer" label and subsequent ramifications. Not to mention 1000 tonnes is still all that's allowed after all of that.

          Something I lack knowledge in...seems to me something in the Mining Act of Ontario says any proceeds of bulk sampling reverts to the province??? I hope I've misunderstood something there, or there's a permit that Sage has applied for that allows them to keep the gold...otherwise there's not much point to the bulk sampling if the gov't gets it all.

          So, I have more questions than answers, sadly, but perhaps someone will be kind enough to enlighten all of us poor sots here.

          ~Q~

          1. I don't know about minimum tonnage to qualify yfor a bulk sample but Brian Maher (at PDAC was talking about 10,000 tonnes (if I remember correctly).

            I am guessing rules differ from province to province. I was in a company based in Val d'or QC that is building a decline down to the main ore zone .... through 2 other gold zones. So as part of the excavation they were also bulk sampling and stock piling ... but as soon as they start processing ore, they are considered a miner and not an explorer. Quebec rebates 50% of exploration costs to explo companies ... so they continue to stockpile until they finish the decline ... and perhaps another.

            PRZ also did several bulk samples on their property as they were suffering from nugget effect ...not sure what permitting was required for that.



            so back to the point re- bulk sampling. I think you just apply for a permit for what you want to do .. within reason. I don't think that 10-20k tonnes is unreasonable.

            but I really have no idea.

            1. Replying to @Tibber

              Thanks for lending some insight...I too am more familiar with the Quebec mining laws oddly enough. I was getting my numbers .....no, not from where you're thinking...but from this site:

              http://www.ontario.ca/en/information...

              But to be honest, I only skimmed through the paragraphs.

              Now, is there any reasons for/against Sage to want to be classified as a miner? Still too early in the game? And what about processing the ore, any way around that, third-party, arms-length type stuff?

              I mean, we've been waiting for something positive to move us along for quite a while...I certainly think the timing would be good to go from an explorer to a producer, however inauspicious a beginning it might have been. If the gold gurus are even halfway close to their predictions, we could see a real surge in prices soon...so why not pull some out of the ground instead of just trying to convince folks we actually have it?

              Even the bigwigs circling ever closer and closer to the BGGC has got me wondering...are they positioning themselves in the summer doldrums before the rest of the market catches on?

              I'm pleased Sage is making progress, at any rate.

              JMO


  3. Yea Red memories i recall those halts on nickel results and the tsx gets hammered and we go no where.

    There can,t be any backlogs in the labs as no one is drilling , would not be surprised to see results by end of June